New Found Gold Expands Queensway Gold Project 2025 Work Program
Highlights:
- 70,000 metres ("m") diamond drill program underway;
- Approximately 11,750 m in 104 DDH1 has been drilled to date, with five drill rigs currently on site;
- 80% of planned drilling focused on resource definition and pre-development work and 20% on exploration;
- The AFZ Core excavation program is underway, with channel sampling of the Iceberg excavation approximately 80% complete and the Lotto excavation commencing shortly;
- A regional exploration program at Queensway South and Queensway North is underway and is expected to run until late September, 2025;
- In addition to a PEA2 planned for release in late Q2/25, the Company is conducting ongoing engineering studies, including metallurgical testwork and trade-off studies; and
- Additional environmental work will be undertaken in 2025 to ensure that all baseline studies are completed for upcoming permitting processes.
Approximately 80% of the planned 2025 drilling at Queensway will be focused on infill drilling of inferred and unclassified mineralization within the pit shells of the AFZ Core portion of the initial mineral resource estimate ("MRE"), grade control drilling at the Keats and Iceberg zones and geotechnical, hydrogeological and condemnation drilling (see the
Approximately 20% of the planned 2025 drilling at Queensway will be focused on exploration, including potential expansions to the initial MRE and new discoveries. This work began in
Dropkick is a new high-grade gold target located 11 kilometres ("km") north of the AFZ Core and open in all directions. Drilling at Dropkick began in late 2024 and therefore was not included in the initial MRE. Highlights from 2024 drilling at Dropkick include:
- 42.8 g/t Au over 14.95 m in NFGC-24-22253,
- 89.5 g/t Au over 5.85 m in NFGC-24-2197 and
- 26.2 g/t Au over 16.15 m in NFGC-24-2193.
For the full results from Dropkick see the
Excavation of the shallow overburden covering the near-surface portion of key zones in AFZ Core began with the Keats zone, which was excavated in 2023 and mapped and sampled in 2024 (see the
The Iceberg zone was excavated over a 220 m by 105 m area in late 2024. The Iceberg zone excavation has exposed broad zones of gold-bearing quartz veins directly below 2.5 to 9 m of overburden. This excavation has been successfully dewatered and channel sampling focused on the key mineralized domains within the excavated area at 7.5 m intervals is approximately 80% complete.
Following the completion of the infill drilling at the Lotto zone, overburden will be excavated to expose the gold-bearing quartz veins. Excavation of the Lotto zone is expected to be completed in Q4/25 and channel sampling is planned for Q2/26.
The Company continues to evaluate the size and location of a bulk sample for the Project within the mineralized zones exposed in the AFZ Core Excavation Program.
The Company has commenced a regional exploration program at Queensway South and Queensway North. This work will focus on the northern and southern extensions of the
On
Additional engineering studies include:
- Metallurgical testing programs are ongoing, with additional work to further refine the flowsheet for the next phase of studies in 2026;
- Condemnation drilling for siting of plant infrastructure, geotechnical and hydrogeological data collection programs are commencing, and required as inputs for the next phase of studies in 2026; and
- Additional trade-off studies to optimize the Project are planned for completion in Q3/25.
The Company will be undertaking additional environmental studies in 2025 as part of its commitment to the Project. Since 2021,
New Found Gold holds a 100% interest in Queensway, located in
The Company has completed an initial MRE at Queensway (see
Recent drilling continues to yield new discoveries along strike and down dip of known gold zones, pointing to the district-scale potential of the 175,600 hectare project that covers a 110 km strike extent along two prospective fault zones.
Please see the Company's website at www.newfoundgold.ca and the Company's SEDAR+ profile at www.sedarplus.ca.
Chief Executive Officer
Follow us on social media at
https://www.linkedin.com/company/newfound-gold-corp
https://x.com/newfoundgold
The scientific and technical information disclosed in this press release was reviewed and approved by
Neither the
This press release contains certain "forward-looking statements" within the meaning of Canadian securities legislation, relating to the expansion of the Company's 2025 work program; engineering and environmental studies and various programs expected to be completed by the Company, including the timing thereof; the AFZ Core Excavation Program and the timing thereof; planned drilling and exploration on the Project and the timing and expected benefits thereof; the initial resource estimate; the preliminary economic assessment and the expected funding, timing and benefits thereof; the advancement of the Project towards development; the interpretation of drilling and assay results, the extent of mineralization and the discovery of zones of high-grade gold mineralization; plans for future exploration and drilling and the focus and timing of same; the merits of the
|
________________________________ |
|
1 DDH = diamond drill holes |
|
2 PEA = preliminary economic assessment |
|
3 Note that the host structures are interpreted to be moderately to steeply dipping and true widths are generally estimated to be 55% to 85% in NFGC-24-2197, 40% to 70% in NFGC-24-2225 and 25% to 55% NFGC-24-2193. Infill veining in secondary structures with multiple orientations crosscutting the primary host structures are commonly observed in drill core which could result in additional uncertainty in true width. Composite intervals reported carry a minimum weighted average of 1 g/t Au diluted over a minimum core length of 2m with a maximum of 4m consecutive dilution when above 200m vertical depth and 2m consecutive dilution when below 200m vertical depth. Included high-grade intercepts are reported as any consecutive interval with grades greater than 10 g/t Au. Grades have not been capped in the averaging and intervals are reported as drill thickness. |
View original content to download multimedia:https://www.prnewswire.com/news-releases/new-found-gold-expands-queensway-gold-project-2025-work-program-302482956.html