Patriot Achieves Further Permitting Progress at the Shaakichiuwaanaan Lithium Project
Federal permitting process progresses and aligns with the Provincial process already underway
Highlights
- Permitting of the
Shaakichiuwaanaan Project is on schedule and progressing well. - The planning phase of the Federal environmental and social impact assessment process is now formally complete, culminating in the
Impact Assessment Agency of Canada (IAAC) publishing its Tailored Impact Statement Guidelines and a detailed Permitting Plan for theShaakichiuwaanaan Lithium Project . - The Permitting Plan is consistent with the Company's previously estimated and reported overall mine authorization timeline.
- This Federal process will run in parallel with the Provincial environmental and social impact assessment process already underway, with submission of the Provincial Environmental and Social Impact Assessment ("ESIA") targeted for late 2025, and the equivalent Federal application to be submitted shortly thereafter.
- The ESIA submissions will be supported by over three years of robust environmental base line data studies and extensive community consultations.
"It can't be underestimated how much work has already been achieved by Patriot to ensure Shaakichiuwaanaan is well-placed in the global lithium raw material development pipeline. Moving the project from discovery and the establishment of a globally significant resource, to the upcoming mine authorization process in less than 4 years is a remarkable achievement that demonstrates both the quality of the Project and team delivering it."
Federal Project Approval Submissions and ESIA Studies
In
In the period since the submission of the Initial Project Description, the Company has engaged with the Federal
The public reference for progress in respect of the IAAC schedule can be found at the following link: https://iaac-aeic.gc.ca/050/evaluations/proj/89271
The Federal impact assessment process will run in parallel with the Provincial permitting process for the Project which commenced in 2023, and will leverage the existing provincial process to streamline the federal requirements to the extent possible.
The Company also notes with interest the efforts of federal authorities to minimize duplication with the provincial approval process. The Company intends to maintain close-contact with all the key Government agencies and the Cree, to ensure a diligent and timely approval process for the Project.
Overall Project Approval Summary Position
Over approximately a 3-year period, extensive environmental baseline data collection field programs and community consultations have been completed as planned to underpin the Company's ESIA (supporting both Federal and Provincial processes), for the development of the CV5 Pegmatite.
As a result of the above, now combined with the constructive and timely approach of regulatory authorities, the provincial ESIA submissions remain on-track for presentation in late 2025, with the federal ESIA to follow shortly thereafter.
Qualified/Competent Person
The information in this news release that relates to exploration results for the Shaakichiuwaanaan Property is based on, and fairly represents, information compiled by Mr. Darren L. Smith,
About
For further information, please contact us at info@patriotbatterymetals.com or by calling +1 (604) 279-8709, or visit www.patriotbatterymetals.com. Please also refer to the Company's continuous disclosure filings, available under its profile at www.sedarplus.ca and www.asx.com.au, for available exploration data.
This news release has been approved by
"
Disclaimer for Forward-looking Information
This press release contains "forward-looking information" or "forward-looking statements" within the meaning of applicable Securities Laws.
All statements, other than statements of present or historical facts, are forward-looking statements. Forward-looking statements involve known and unknown risks, uncertainties and assumptions and accordingly, actual results could differ materially from those expressed or implied in such statements. You are hence cautioned not to place undue reliance on forward-looking statements. Forward-looking statements are typically identified by words such as "plan", "development", "growth", "continued", "intentions", "expectations", "strategy", "opportunities", "anticipated", "trends", "potential", "outlook", "ability", "additional", "on track", "prospects", "viability", "estimated", "reaches", "enhancing", "strengthen", "target", "will", "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved.
________________________________ |
1
Determination based on Mineral Resource data, sourced through |
2
The Consolidated MRE cut-off grade is variable depending on the mining method and pegmatite (0.40% Li2O open-pit, 0.60% Li2O underground CV5, and 0.70% Li2O underground CV13). A grade constraint of 0.50% Cs2O was used to model the Rigel and |
Although the Company believes its expectations are based upon reasonable assumptions and has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. As such, these risks are not exhaustive; however, they should be considered carefully. If any of these risks or uncertainties materialize, actual results may vary materially from those anticipated in the forward-looking statements found herein. Due to the risks, uncertainties and assumptions inherent in forward-looking statements, readers should not place undue reliance on forward-looking statements.
Readers are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. Forward-looking statements are also subject to risks and uncertainties facing the Company's business, any of which could have a material adverse effect on the Company's business, financial condition, results of operations and growth prospects. Some of the risks the Company faces and the uncertainties that could cause actual results to differ materially from those expressed in the forward-looking statements include, among others, the ability to execute on plans relating to the Company's Project, including the timing thereof as well as its permitting process. In addition, readers should review the detailed risk discussion in the Company's most recent Annual Information Form filed on SEDAR+ for a fuller understanding of the risks and uncertainties that affect the Company's business and operations.
The forward-looking statements contained herein are made only as of the date hereof. The Company disclaims any intention or obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise, except to the extent required by applicable law. The Company qualifies all of its forward-looking statements by these cautionary statements.
Competent Person Statement (ASX Listing Rule 5.23)
The mineral resource estimate in this release was reported by the Company in accordance with ASX Listing Rule 5.8 on
View original content to download multimedia:https://www.prnewswire.com/news-releases/patriot-achieves-further-permitting-progress-at-the-shaakichiuwaanaan-lithium-project-302545668.html
SOURCE