Blue Sky Uranium Completes Comprehensive GAP Analysis for Ivana Deposit and Identifies Clear Roadmap to Feasibility
OTCQB Venture Market (OTC): BKUCF
The Gap Analysis was prepared by
Using the existing Preliminary Economic Assessment ("PEA") as the baseline, the GAP Analysis provides a clear, actionable roadmap for advancing Ivana through the Pre-Feasibility Study ("PFS") stage and potentially onward to the completion of a Feasibility Study ("FS") and submission of the final Environmental Impact Assessment for Ivana. The timeline established by the roadmap is approximately 24 months to complete these steps, with an estimated overall budget of
GAP Analysis Summary
The objective of the Gap Analysis was to identify technical, environmental, social, and regulatory areas where additional data collection, studies, or design are needed to support a PFS and FS. The baseline for all technical assessments was the PEA and updated Mineral Resource Estimate ("MRE") for the Ivana deposit described in the NI 43-101 Technical Report dated
The Gap Analysis report confirms that Ivana benefits from strong baseline technical work, favorable metallurgy, clear permitting pathways, and a well-defined execution plan. The report provides a structured timeline to advance key areas in order to support a PFS and FS for Ivana:
-
Mineral Resources: IMSA completed a new infill drilling program this year, totaling 328 RC holes, to support potentially further upgrading the category of some or all of the resource (currently ~80% of the MRE is in Indicated). Integrating this infill program with the previous block model will help define future drilling requirements, if needed, to establish mineral reserves for the FS.
-
Mineral Processing: Previous alkaline leach metallurgical tests have shown excellent uranium recoveries after low-cost scrubbing and screening preconcentration. The GAP analysis recommended repetition of leach testwork, further optimization of beneficiation, solvent extraction and downstream precipitation testing, additional process step testing and confirmation that the brine/brackish water available on site can be used in the processing flowsheet. The additional proposed mineral processing testwork is expected to take about 15 to 16 months and represents the most significant critical-path item to support the project's advancement.
-
Hydrogeological,
Radiological, and Geotechnical Baseline: Hydrogeological studies began in 2017, with baseline studies completed between 2021 and 2023 and updated in 2024 through 2025. The GAP Analysis recommends supplementary programs to strengthen these baseline datasets and ensure they are fully aligned with upcoming permitting milestones.
-
Surface Water, Groundwater, Geochemistry, Tailings, Closure/Rehab
: The Gap Analysis identifies work related to surface and groundwater studies, along with the need for additional geochemical characterization of ore and waste materials, further definition for tailings design, and the related inputs that will support closure and rehabilitation planning at the PFS/FS stages.
-
Infrastructure: No significant infrastructure constraints were identified, allowing engineering activities to proceed in parallel with technical studies related to access roads, site buildings, power supply, and more.
-
Biodiversity,
Archaeology,
and Paleontology: Baseline surveys began in 2021 and have provided proper characterization. The report recommends maintaining and reinforcing these surveys for a more detailed understanding.
- Communities: Social studies conducted in recent years are considered sufficient at this stage. The report suggests further work to consolidate the socioeconomic baseline and implement specific programs.
In addition to identifying technical requirements, the study provides a high-confidence development framework that reduces execution risk and establishes a clear path to Feasibility Study level, culminating in the submission of an Environmental Impact Assessment report to the regulatory authorities. Key milestones in the path include:
- Q4 2025: Metallurgical lab selection and sample shipment; initiation of mineral resources update
- Q2 2026: Preliminary metallurgical results and commencement of extended metallurgical tests
- Q3 2026: PFS level of engineering
- Q3 2026: Final mineral resource report and PFS completion
- Q2 2027: Final Metallurgical test report and FS completion
- Q3 2027: EIA submission
The total cost to complete the required technical, environmental, and permitting studies up to the Feasibility Study level is estimated at
Qualified Persons
The technical contents of this news release have been reviewed and approved by Mr.
About
About
ON BEHALF OF THE BOARD
"
______________________________________
Neither
This news release may contain forward-looking statements and forward-looking information (collectively, the "forward-looking statements") within the meaning of applicable securities laws. Forward-looking statements address future events and conditions and therefore involve inherent risks and uncertainties. Any statements that are contained in this press release that are not statements of historical fact may be deemed to be forward-looking statements. Forward-looking statements are often identified by terms such as "may", "should", "anticipate", "will", "estimates", "believes", "intends" "expects" and similar expressions which are intended to identify forward-looking statements. More particularly and without limitation, this press release contains forward-looking statements that, other than statements of historical fact, address activities, events or developments the Company believes, expects or anticipates will or may occur in the future, including, without limitation, statements about the GAP Analysis providing a clear, actionable roadmap for advancing Ivana through the PFS stage and potentially onward to the completion of a Definitive Feasibility Study DFS and submission of the final Environmental Impact Assessment for Ivana, the timeline established by the roadmap being approximately 24 months to complete these steps, with an estimated overall budget of
Forward-looking statements are subject to a number of risks and uncertainties that may cause the actual results of the Company to differ materially from those discussed in the forward-looking statements and, even if such actual results are realized or substantially realized, there can be no assurance that they will have the expected consequences to, or effects on, the Company. Factors that could cause actual results or events to differ materially from current expectations include, among other things: uncertainty relating to mineral resources; risks related to heavy metal and transition metal price fluctuations, particularly uranium and vanadium; risks relating to the dependence of the Company on key management personnel and outside parties; the potential impact of global pandemics; risks and uncertainties related to governmental regulation and the ability to obtain, amend, or maintain licenses, permits, or surface rights; risks associated with technical difficulties in connection with mining activities; and the possibility that future exploration, development or mining results will not be consistent with the Company's expectations, including in respect of the Company's planned exploration program described in this news release. Actual results may differ materially from those currently anticipated in such statements. Readers are encouraged to refer to the Company's public disclosure documents for a more detailed discussion of factors that may impact expected future results. The forward-looking statements contained in this press release are made as of the date of this press release, and the Company does not undertake any obligation to update publicly or to revise any of the included forward-looking statements, whether as a result of new information, future events or otherwise, except as expressly required by securities law.
View original content to download multimedia:https://www.prnewswire.com/news-releases/blue-sky-uranium-completes-comprehensive-gap-analysis-for-ivana-deposit-and-identifies-clear-roadmap-to-feasibility-302626379.html
SOURCE