Electric Upgrades Boost Reliability for McKean County Customers
Work part of
New underground cable for three power lines served by a local substation is helping to reduce outages, speed power restoration and support local growth. The project builds on work completed in 2024, when Penelec installed a new substation transformer that delivers more electricity and better meets the community's power needs.
John Hawkins, FirstEnergy
Upgrades That Deliver Impact
The work includes:
- Installing stronger cables: New, bigger underground wires can carry more electricity to local homes and businesses.
- Adding backup capabilities: Redundant power lines mean customers can be switched to another line to minimize power outages when issues arise.
- Protecting new equipment: Sturdy plastic pipes better protect underground power lines from water, road salt and corrosive soil to keep electricity more reliable.
- Completing additional upgrades in 2026: Adjustments to existing pole-top equipment in the coming year will make it easier to reroute electricity and further reduce outages.
Photos of the underground cable installation are available on Flickr .
Part of a Larger Plan
The upgrades are part of FE PA's Long Term Infrastructure Improvement Plan (LTIIP) III, which fast-tracks important investments in electric system reliability. The LTIIP III investment for Penelec's service area is
LTIIP is part of Energize365, FirstEnergy's long-term investment program to modernize the electric grid. FirstEnergy plans to invest
Penelec serves approximately 597,000 customers within 17,600 square miles of northern and central
FirstEnergy is dedicated to integrity, safety, reliability and operational excellence. Its electric distribution companies form one of the nation's largest investor-owned electric systems, serving more than six million customers in