Hut 8 Commercializes First Phase of 1 GW Beacon Point AI Data Center Campus with 15-Year, 352 MW IT Lease with Base-Term Contract Value of $9.8 Billion
Triple-net lease with high-investment-grade tenant valued at up to
Transaction expands
Hut 8 to deliver a 352 MW AI factory designed to NVIDIA's DSX reference architecture for gigawatt-scale AI infrastructure
Executed under Hut 8's repeatable delivery model with Tier 1 counterparties:
Transaction Highlights
- Lease Structure: Triple net (NNN) lease.
- Tenant Profile: Confidential, high-investment-grade company.
- Compute Architecture: Hut 8 to deliver a 352 MW AI factory designed to NVIDIA's DSX reference architecture for gigawatt-scale AI infrastructure.
-
Base-Term Contract Value: Total contract value of
$9.8 billion over a 15-year base lease term, inclusive of a 3.0% annual base rent escalator. -
NOI Contribution: Expected cumulative NOI contribution of
$9.8 billion over the base lease term, translating to an expected average annual NOI contribution of$655 million upon stabilization. -
Upside Economics: Three 5-year renewal options increase potential contract value to approximately
$25.1 billion assuming all three options are exercised. - Delivery Timeline: Initial data hall delivery expected in Q3 2027.
-
Project-level Financing: Hut 8 intends to support the development of
Beacon Point with project-level financing that aims to optimize cost of capital at the asset level while maintaining disciplined long-term leverage metrics at the corporate level. - Campus Scalability: 1,000 MW of utility capacity with initial energization expected in Q1 2027.
- Commercial Potential: The lease for 352 MW of IT capacity, requiring approximately 500 MW of utility capacity, represents the first phase of commercialization at a campus designed to support up to 1,000 MW of utility capacity, providing significant runway for potential campus expansion and revenue growth.
Power-
Asher Genoot, CEO of Hut 8, said: "
First-Principles Engineering and the Second Phase of Value Creation
Scalable, Partnership-Driven Execution Model
Hut 8 is developing
Asher Genoot, CEO of Hut 8, said: "This transaction commercializes the first building of our newest gigawatt-scale campus and marks our second AI data center lease. More importantly, it demonstrates that our development model, which pairs power-first underwriting with disciplined commercialization and institutional execution, is repeatable and extendable across our broader pipeline."
NVIDIA is engaged as technology partner, with Phase 1 of the campus engineered to NVIDIA's DSX reference architecture for gigawatt-scale AI factories. Jacobs, a global scienced-based consulting and advisory firm, is retained as EPCM (Engineering, Procurement and Construction Management) lead, working alongside Vertiv in its role supporting critical digital infrastructure systems.
Utility and Regional Partnerships
Hut 8 is developing the
Hut 8 brings a long operating history in
Development Pipeline Update
The Transaction advances 500 MW of utility capacity from
Hut 8 continues to advance opportunities across a broader pipeline spanning 7,545 MW of Energy Capacity Under Diligence, Exclusivity, and Development, applying the same power-first underwriting framework and institutional execution model demonstrated at River Bend and
|
Stage |
Description |
Utility Capacity
|
|
Energy Capacity Under |
Sites identified for large-load use cases such as AI, HPC, ASIC compute, industrial applications such as |
5,315 MW |
|
Energy Capacity Under |
Sites where Hut 8 has secured a clear path to ownership through either: (i) an exclusivity agreement that prevents |
1,680 MW1 |
|
Energy Capacity Under |
Sites where Hut 8 is actively investing in development and commercialization by executing definitive land and/or |
550 MW |
|
Energy Capacity Under |
Sites where Hut 8 has executed a definitive offtake agreement and commenced construction activities. |
830 MW |
|
Total |
All sites under diligence, exclusivity, development, commercialization, and construction. |
8,375 MW 1 |
|
|
|
Note: (1) Excludes 1,000 MW of potential IT expansion capacity at River Bend, for which Fluidstack holds a ROFO under the River Bend lease. |
Non-GAAP Financial Measures
This press release includes a non-GAAP financial measure, expected net operating income (NOI) contribution, which the Company defines as expected lease revenue for a particular lease less any non-reimbursable operating expenses attributable to the leased property. The Company's management team uses expected NOI contribution to measure the expected operating performance of a particular lease. Operating income is the GAAP measure most directly comparable to expected NOI contribution. In evaluating expected NOI contribution, you should be aware that in the future the Company may incur non-reimbursable lease operating expenses that are not currently known. The Company's presentation of expected NOI contribution should not be construed as an inference that its future results will be unaffected by unusual or non-recurring items. Expected NOI contribution has important limitations as an analytical tool and you should not consider expected NOI contribution in isolation or as a substitute for analysis of results as reported under GAAP. For example, expected NOI contribution excludes the impact of selling, general and administrative expenses and depreciation and amortization, which have real economic effect and could materially impact the Company's consolidated financial results. Other companies, including Real Estate Investment Trusts, may calculate expected NOI contribution differently than the Company does and, accordingly, the Company's expected NOI contribution may not be comparable to similar measures published by such companies. No reconciliation of expected NOI contribution is included in this press release because the Company is unable to quantify certain amounts that would be required to be included in operating income without unreasonable efforts as such quantification would imply a degree of precision that would be confusing or misleading to investors.
Hut 8 has made available on its website an investor presentation with further details regarding the Transaction.
For important news and information regarding the Company, including investor presentations and timing of future investor conferences, visit the Investor Relations section of the Company's website, hut8.com/investors, and its social media accounts, including on X and LinkedIn. The Company uses its website and social media accounts as primary channels for disclosing key information to its investors, some of which may contain material and previously non-public information.
About Hut 8
Hut 8 is an energy infrastructure platform integrating power, digital infrastructure, and compute at scale to fuel next-generation, energy-intensive technologies such as AI, high-performance computing, and ASIC compute. The Company develops, commercializes, and operates industrial-scale energy and data center infrastructure through a power-first, innovation-driven approach. For more information, visit hut8.com.
Cautionary Note Regarding Forward-Looking Information
This press release includes "forward-looking information" and "forward-looking statements" within the meaning of Canadian securities laws and
Statements containing forward-looking information are not historical facts, but instead represent management's expectations, estimates, and projections regarding future events based on certain material factors and assumptions at the time the statement was made. While considered reasonable by Hut 8 as of the date of this press release, such statements are subject to known and unknown risks, uncertainties, assumptions and other factors that may cause the actual results, level of activity, performance, or achievements to be materially different from those expressed or implied by such forward-looking information, including, but not limited to, risks relating to the construction of new data centers, including cost overruns, delays, supply chain issues, permitting or regulatory hurdles, unexpected technical challenges, and dependency on contractors; risks relating to the financing of new data centers, including the potential dilutive impact of equity issuances (if any), access to capital markets, timing and cost of financing, and market conditions such as increases in interest rates, declining equity valuations, volatility in credit markets, or tightening lending standards; risks impacting our ability to expand the power capacity at the River Bend campus, such as limitations of transmission and/or generation resources; failure of critical systems; geopolitical, social, economic, and other events and circumstances; competition from current and future competitors; risks related to power requirements; cybersecurity threats and breaches; hazards and operational risks; changes in leasing arrangements; Internet-related disruptions; dependence on key personnel; having a limited operating history; attracting and retaining customers; entering into new offerings or lines of business; price fluctuations and rapidly changing technologies; predicting facility requirements; strategic alliances or joint ventures; operating and expanding internationally; failing to grow hashrate; purchasing miners; relying on third-party mining pool service providers; uncertainty in the development and acceptance of the Bitcoin network; Bitcoin halving events; competition from other methods of investing in Bitcoin; concentration of Bitcoin holdings; hedging transactions; potential liquidity constraints; legal, regulatory, governmental, and technological uncertainties; physical risks related to climate change; involvement in legal proceedings; trading volatility; and other risks described from time to time in Company's filings with the U.S. Securities and Exchange Commission. In particular, see the Company's recent and upcoming annual and quarterly reports and other continuous disclosure documents, which are available under the Company's EDGAR profile at sec.gov and SEDAR+ profile at sedarplus.ca.
View original content to download multimedia:https://www.prnewswire.com/news-releases/hut-8-commercializes-first-phase-of-1-gw-beacon-point-ai-data-center-campus-with-15-year-352-mw-it-lease-with-base-term-contract-value-of-9-8-billion-302763484.html