Duke Energy files 2025 Carolinas Resource Plan, continues modernizing energy infrastructure to support future growth
- Update to the long-range plan approved by
North Carolina andSouth Carolina regulators last year supports economic success of both states - Plan meets significant growth while saving customers money – future bill impacts are below inflation
The 2025 Carolinas Resource Plan is Duke Energy's road map to serve customer growth needs while protecting reliability and keeping costs as low as possible. Customer bill impacts for the proposed plan are projected to average 2.1% annually over the coming decade – lower than the rate of inflation and significantly less than projected costs for the previously approved plan.
Our view:
"
The big picture:
The plan reflects rising electricity demand across the Carolinas at an unprecedented pace, driven by the economic success of
Across the Carolinas, customer energy needs over the next 15 years are expected to grow at eight times the growth rate of the prior 15 years. To put this in perspective, that projected increase in energy use is more than double the growth forecasted when the 2023 Carolinas Resource Plan was initially filed.
The 2025 Carolinas Resource Plan also adapts to significant policy changes at state and federal levels. Recent energy legislation in both states emphasizes reliability, while changes in federal regulations and tax credits support advanced nuclear and battery storage and provide flexibility for existing coal and new natural gas generation.
To minimize the plan's future costs for customers while maintaining reliability and powering growth, the company's recommended energy mix has evolved accordingly. Compared to the prior plan, changes in proposed resource actions include:
-
Nuclear: added large light-water reactor (LLWR) technology for evaluation in addition to small modular reactors (SMRs), targeting potential 2037 in service for new nuclear generation at either
Belews Creek, N.C. (SMR) or the W.S.Lee site inCherokee County, S.C. (LLWR), expanding license activities to include both LLWR and SMR sites to preserve optionality. -
Natural gas: maintained the five combined-cycle (CC) units called for in 2023 modeling for baseload generation and increased the number of combustion turbines (CT) for peak needs by two to a total of seven, helping meet continued load growth; added enhanced liquified natural gas storage to reduce fuel cost volatility and boost reliability.
- Locations: CCs –
Person County, N.C. (2),Anderson County, S.C. (1), third site to be determined (2); CTs –Catawba County, N.C. (2),Rowan County, N.C. (2),Richmond County, N.C. (1), fourth site to be determined (2).
- Locations: CCs –
-
Solar: targeted 4,000 megawatts (MW) by 2034, maintaining the 2025 procurement target to maximize customer benefits of the remaining federal energy tax credits for solar.
- Locations: to be determined through annual competitive bidding process.
-
Battery storage: expanded to 5,600 MW targeted by 2034 – an increase of 2,900 MW over the 2023 plan's projection through 2031 – to meet near-term growth and leverage tax credits that provide savings for customers.
- Locations: across the Carolinas, including the Allen, Riverbend and Mayo coal plant sites.
- Wind: not an economically viable resource for customers through 2040 but will be reassessed at next plan update.
-
Pumped storage hydro: limited near-term development of a second power block at
Bad Creek to preserve optionality and take advantage of tax credits; deferred in-service target from 2034 to 2040 to reduce grid upgrade costs and accelerate in-service dates for crucial near-term projects including solar already in development, natural gas, hydro and batteries. -
Coal: following federal actions that eased restrictions on coal generation, targeted potential two- to four-year extensions of units that have dual-fuel capability (
Belews Creek ,Cliffside ,Marshall ). Maintaining an orderly exit from coal as approved by state regulators, while extending the operational life of these fuel-flexible assets for a short time, will help meet load growth.
Yes and:
"We've also made further progress in maximizing the value of existing resources, making them more efficient and able to deliver more electricity to meet near-term growth needs while minimizing costs to customers," Bowman said.
For example, the company is:
- Adding nearly 300 MW of clean capacity to the grid – the equivalent of a new SMR – through power uprate projects at four nuclear stations.
- Already upgraded the capacity of
Bad Creek pumped storage by another 280 MW and is recommending upgrades to seven other emissions-free hydro plants. - Upgrading its natural gas fleet in a manner that reduces fuel costs and emissions.
As is the case with this two-year update, all resource amounts and target dates will be updated in future filings, allowing Duke Energy to continue adapting to technological advances, federal and state incentives and policy changes, and other factors beneficial to customers.
Flashback:
The plan builds upon the 2023 Carolinas Resource Plan approved by
What's next:
Duke Energy Carolinas
Duke Energy Progress
Duke Energy
Duke Energy (NYSE: DUK), a Fortune 150 company headquartered in
Duke Energy is executing an ambitious energy transition, keeping customer reliability and value at the forefront as it builds a smarter energy future. The company is investing in major electric grid upgrades and cleaner generation, including natural gas, nuclear, renewables and energy storage.
More information is available at duke-energy.com and the Duke Energy News Center. Follow Duke Energy on X, LinkedIn, Instagram and Facebook, and visit illumination for stories about the people and innovations powering our energy transition.
Contact:
24-hour media line: 800.559.3853
View original content to download multimedia:https://www.prnewswire.com/news-releases/duke-energy-files-2025-carolinas-resource-plan-continues-modernizing-energy-infrastructure-to-support-future-growth-302572373.html
SOURCE Duke Energy