Company Announcements

Rio Tinto progresses Oyu Tolgoi power options

Source: RNS
RNS Number : 2751D
Rio Tinto PLC
18 February 2020
 

Rio Tinto progresses Oyu Tolgoi power options

 

17 February 2020

 

Rio Tinto continues to progress options to secure domestically sourced power for the Oyu Tolgoi copper mine in Mongolia, which it is obliged to do by 30 June 2023 under the 2009 Investment Agreement (IA) between Turquoise Hill, the Government of Mongolia and Rio Tinto and subsequent Power Sector Framework Agreement, signed in 2018.

 

In compliance with these agreements, Oyu Tolgoi LLC today submitted to the Government of Mongolia a Feasibility Study for the Tavan Tolgoi Power Plant (TTPP) Project, which involves building a 300 MW coal power plant. In parallel with the TTPP Project, and in consultation with the Government of Mongolia, Rio Tinto is also progressing alternative options to source domestic power, including a renewable power component.

 

Rio Tinto Copper & Diamonds chief executive Arnaud Soirat said "Rio Tinto, Turquoise Hill and the Government of Mongolia are all committed to securing a reliable and long term domestic power source for the Oyu Tolgoi mine and are working together to achieve this".

 

The TTPP Feasibility Study envisages a 300 MW power plant with a project cost estimate of around $924 million. This is already included in the group capex guidance of $7 billion in 2020 and $6.5 billion each in 2021 and 2022.

 

 



 

Contacts

 

media.enquiries@riotinto.com 

riotinto.com 

 

  Follow @RioTinto on Twitter

 

 

Media Relations, United Kingdom

Illtud Harri

M +44 7920 503 600

 

David Outhwaite

T +44 20 7781 1623

M +44 7787 597 493

 

Media Relations, Americas

Matthew Klar

T +1 514 608 4429

 

Media Relations, Asia

Grant Donald

T +65 6679 9290

M +65 9722 6028

 

Media Relations, Australia

Jonathan Rose

T +61 3 9283 3088

M +61 447 028 913

 

Matt Chambers

T +61 3 9283 3087

M +61 433 525 739

 

Jesse Riseborough

T +61 8 6211 6013

M +61 436 653 412

 

Investor Relations, United Kingdom

Menno Sanderse
T: +44 20 7781 1517
M: +44 7825 195 178

 

David Ovington

T +44 20 7781 2051

M +44 7920 010 978

 

 

Investor Relations, Australia

Natalie Worley

T +61 3 9283 3063

M +61 409 210 462

 

Amar Jambaa

T +61 3 9283 3627
M +61 472 865 948

 

Rio Tinto plc

6 St James's Square

London SW1Y 4AD

United Kingdom

T +44 20 7781 2000

Registered in England

No. 719885

 

Rio Tinto Limited

Level 7, 360 Collins Street

Melbourne 3000

Australia

T +61 3 9283 3333

Registered in Australia

ABN 96 004 458 404


This announcement is authorised for release to the market by Steve Allen, Rio Tinto's Group Company Secretary.

 


This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
MSCFFFIFFSIDLII