- A high level of dam safety is always our top priority. The new direction naturally entails challenges in the short term, but it also creates long-term opportunities in Aitik and a clear direction for how the business can be developed going forward, says
Normally, the dam structures at Aitik's tailings pond are built and filled in line with production. In connection to ongoing geotechnical surveys for future dam heightening, areas with poorer soil conditions than previously estimated have been identified. Additional dam heightening and deposition of tailings against dams in these areas has therefore been suspended. In a first step, existing dam structures will now be strengthened and certain infrastructure will need to be moved. This is estimated to take about two years, after which dam heightenings and deposition in this area can be resumed.
Production in Aitik is not expected to be affected during this time as tailings can continue to be deposited in other parts of the tailings pond. The measures depend on environmental permits and other approvals, but work can be started prior to the permitting process.
For 2022, the total investments in the Group are now expected to increase from previously communicated just over
This information is information that
For further information, please contact:
Mail: klas.nilsson@boliden.com
Due to this communicated press release, a telephone conference for analysts will be held today at 09.00
To participate, please call 5 minutes before the opening of the conference:
- from
Sweden +46 856642651 -
from
United Kingdom +44 3333000804 - from
United States +1 6319131422
PIN Code: 69409035#
The presentation will be held in English
This information was brought to you by Cision http://news.cision.com
https://news.cision.com/boliden/r/decision-to-adjust-dam-construction-in-aitik,c3543838
The following files are available for download:
Press release (PDF) |
View original content:https://www.prnewswire.com/news-releases/decision-to-adjust-dam-construction-in-aitik-301522532.html
SOURCE