LUCARA ANNOUNCES Q3 2024 RESULTS; SIGNIFICANT SHAFT SINKING PROGRESS
Q3 2024 HIGHLIGHTS
- Recoveries of two exceptional diamonds larger than 1,000 carats, including the epic 2,488-carat(1) diamond and the 1,094-carat diamond.
- A total of 116,221 carats of diamonds were sold, generating revenue of
$44.3 million in Q3, 2024. - On
October 4, 2024 , the Company sold its interest inClara Diamond Solutions Limited Partnership ,Clara Diamond Solutions B.V. , and Clara Diamond Solutions GP (together referred to as "Clara") for approximately$3.0 million in cash, the return of 10,000,000 Lucara common shares, as well as the transfer of liabilities tied to sales performance metrics and a change of control, thereby eliminating a share issuance obligation of 13,400,000 Lucara common shares. - Karowe registered no lost time injuries during the three months ended
September 30, 2024 . As ofSeptember 30, 2024 , the mine had operated over three years without a lost time injury. - Significant progress was made in shaft sinking and lateral development connecting the production and ventilation shafts, with the critical path ventilation shaft being ahead of the
July 2023 rebase schedule. At the end of Q3, the production shaft had reached a depth of 686 metres and the ventilation shaft a depth of 582 metres below surface ("mbs"). - A total of 104,390 carats were recovered in Q3, 2024, including 96,597 carats from direct ore feed from the pit and stockpiles, at a recovered grade of 13.4 carats per hundred tonnes ("cpht") and an additional 7,793 carats recovered from processing of historic recovery tailings.
- A total of 244 Specials (defined as rough diamonds larger than 10.8 carats) were recovered during the quarter, with 12 diamonds greater than 100 carats, including three stones greater than 300 carats. The recovery of 244 Specials equated to 11.28% by weight of the total recovered carats from ore processed in Q3, 2024. This weight percentage of Specials exceeded the Company's expectation and was heavily influenced by the recovery of the 2,488-carat and 1,094-carat stones.
- Operational highlights from the
Karowe Mine included:- Ore and waste mined of 0.8 million tonnes ("Mt") (Q3, 2023: 0.9Mt) and 0.2Mt (Q3, 2023: 1.0Mt), respectively.
- 0.7 Mt of ore processed (Q3, 2023: 0.7Mt).
- Financial highlights for Q3, 2024 included:
- Operating margins of 48% were achieved (Q3, 2023: 63%). Lower operating margins resulted from the decrease in revenue realized for the quarter.
- Operating cost per tonne processed(2) was
$27.34 , a decrease of 5% compared to Q3, 2023 cost per tonne processed of$28.84 . The continued impact of inflationary pressures, particularly labour, has been well managed by the operation. A strongU.S. dollar continues to offset a small increase in costs over the comparable period.
- During Q3, 2024, the Company invested
$24.1 million into theKarowe Underground Project ("UGP"), excluding capitalized cash borrowing costs:- During Q3, 2024, the ventilation shaft completed 169 metres of lateral development and 28 metres of sinking advance.
- Production shaft activities included sinking a total of 130 metres, and completion of 3 water probe hole covers.
- Cash position and liquidity as at
September 30, 2024 :- Cash and cash equivalents of
$23.6 million . - Working capital (current assets less current liabilities excluding assets and liabilities held for sale) of
$22.3 million . $180.0 million drawn on the$190.0 million Project Facility ("Project Facility") for the Karowe UGP with$25.0 million drawn on the$30.0 million working capital facility ("WCF") and a funded Cost Overrun Reserve Account ("CORA") balance of$43.7 million .
- Cash and cash equivalents of
(1) The carats reflect the final cleaned weight of the rough stone. The stone was previously reported at 2,492-carats. |
(2) Operating cash cost per tonne processed and adjusted EBITDA are non-IFRS measures (See "Use of Non-IFRS Financial Performance Measures" in MD&A). |
These historic recoveries reflect the culmination of our unwavering commitment to operational excellence and our industry-leading safety standards. Our open pit operations continue to deliver consistent results, while the underground expansion project has achieved significant milestones, particularly in shaft sinking activities during the quarter. This progress is testament to our team's technical proficiency and dedication to executing complex mining projects.
Looking ahead, Lucara's strategic positioning in the diamond sector remains robust. The ongoing development of the Karowe underground project represents a pivotal investment in our future, designed to extend mine life and maintain our exceptional stone production profile.
As we progress through this transformative period, we remain focused on executing our strategic objectives while maintaining our position as an industry leader in the recovery and marketing of exceptional diamonds. The recent discoveries reinforce our confidence in Karowe's potential and our ability to deliver long-term value to our shareholders."
The long-term natural diamond prices outlook remains resilient due to favourable supply and demand dynamics due to decreasing production volumes from major operating mines. However, the smaller size stones market remains soft as demand is impacted by a weak Asian market and the increasing uptake of laboratory-grown diamonds. Demand for stones larger than 10.8 carats remains robust, as reflected in the Company's sales in the plus 10.8 carats category. The G7 sanctions on Russian diamonds over one carat, effective
Prices of laboratory-grown diamonds have continued to decrease in 2024 with production outweighing demand for these products. In mid-2024, De Beers announced it will cease creating synthetic diamonds and will instead direct its efforts to sell natural diamonds. This is in conjunction with several major brands confirming that they would no longer market laboratory-grown diamonds. The longer-term market fundamentals for natural diamonds remain positive as demand is expected to outpace future supply, as supply has been declining globally over the past few years.
Karowe diamonds are sold through three sales channels: through a diamond sales agreement concluded with HB Antwerp ("HB"), on the Clara digital sales platform and through quarterly tenders.
HB Sales
Karowe's large, high value diamonds have historically accounted for approximately 60% to 70% of Lucara's annual revenues. In
A 'top-up' payment is due to the Company when HB's final polished diamond sales price exceeds the initial estimated price. Conversely, if the final sale price is lower than estimated (after HB's fees), HB receives a refund of the difference. These top-up payments, which mainly relate to diamonds from previous quarters, are paid after deducting HB's fees. The timing and amount of these payments vary based on diamond complexity and initial planning assumptions. Throughout manufacturing, stones undergo reassessment, potentially leading to plan adjustments aimed at maximizing final sale prices while considering market demand for the polished product.
For accounting purposes, the transaction price includes estimates of both final polished sales price and top-up payments, net of HB's fees and manufacturing costs. These estimates are updated each period end until the final transaction price is confirmed.
Sethunya Diamond
Sethunya, a 549-carat stone recovered in 2020, distinguished by its considerable size and quality is subject to a separate agreement with HB. Lucara received an advance of future proceeds of
Quarterly Tenders
All +10.8 carat non-gem quality diamonds and all diamonds less than 10.8 carats which are not sold on the Clara platform are sold as rough diamonds through quarterly tenders. Viewings take place in both
Clara
Clara is a secure web-based digital marketplace which is designed to transact single diamonds between 1 and 10 carats, in higher colours and quality.
On
KAROWE UNDERGROUND PROJECT UPDATE
The Karowe UGP is designed to access the highest value portion of the Karowe orebody, with initial underground carat production predominantly from the eastern magmatic/pyroclastic kimberlite (south) ("EM/PK(S)") unit. The Karowe UGP is expected to extend the mine life to beyond 2040.
An update to the Karowe UGP schedule and budget was announced on
With the 2023 update to the UGP schedule and budget, the
During Q3, 2024, the UGP achieved a twelve-month rolling Total Recordable Injury Frequency Rate of 0.65. The UGP Total Recordable Injury Frequency Rate at
The ventilation shaft Q3, 2024 development:
- Reached 582 mbs out of a planned final depth of 722 metres.
- Continued 470-level(2) station development.
The production shaft Q3, 2024 development:
- Reached 686 mbs, out of a planned final depth of 770 metres.
Related infrastructure Q3, 2024 development:
- Completed the construction and pre-commissioning of the permanent bulk air coolers at the production shaft in
July 2024 . - Construction and fabrication of the permanent man and materials winder continued during the quarter, representing the last major component for the permanent winders.
- Commenced the adjudication and review of underground lateral development tender documents.
- Advanced mining engineering with a focus on supporting shaft sinking, underground infrastructure engineering, finalizing drilling level plans and placed shaft steelwork orders in
October 2024 .
The capital cost expenditure for the UGP in 2024 is expected to be up to
Activities planned for the Karowe UGP in Q4 2024 include the following:
- Production shaft sinking to 310-level(2) and ventilation shaft to 335-level(2).
- Complete 470-level(2) station structural construction work, 670-level(2) electrical substation and sump construction.
- Procurement of underground equipment, including an additional Load, Haul, Dump vehicle for the production shaft station development. Major components of the underground crusher and dewatering pumps will be delivered to site.
- Continuation of detailed design and engineering of the underground mine infrastructure, drawbells and underground layout.
- Construction of the man-and-material winder civils and structural building.
(2) Each level is equivalent to a metre above sea level. |
FINANCIAL HIGHLIGHTS – Q3 2024
|
|
Three months ended |
Nine months ended |
||||
In millions of |
|
2024 |
2023 |
2024 |
2023 |
||
|
|
|
|
|
|
||
Revenues |
$ |
44.3 |
$ 56.3 |
$ 125.1 |
$ 136.1 |
|
|
Operating expenses |
|
(23.1) |
(20.5) |
(55.1) |
(51.3) |
||
Net income from continuing operations for the period |
|
0.2 |
11.7 |
5.1 |
19.6 |
||
Net loss from discontinued operations for the period |
|
(0.7) |
(1.1) |
(2.2) |
(3.1) |
||
Earnings per share from continuing operations (basic and diluted) |
$ |
0.00 |
$ 0.03 |
0.01 |
0.04 |
||
|
|
|
|
|
|
||
Cash on hand |
|
|
|
23.6 |
16.8 |
||
CORA |
|
|
|
43.7 |
18.4 |
||
Amounts drawn on WCF |
|
|
|
25.0 |
35.0 |
||
Amounts drawn on Project Facility |
|
|
|
$ 180.0 |
$ 90.0 |
||
|
|
|
|
|
|
||
Carats sold |
|
116,221 |
111,673 |
286,970 |
267,763 |
||
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
QUARTERLY RESULTS FROM OPERATIONS – KAROWE MINE
|
UNIT |
Q3-24 |
Q2-24 |
Q1-24 |
Q4-23 |
Q3-23 |
Sales |
|
|
|
|
|
|
Revenues from the sale of Karowe diamonds |
US$M |
44.3 |
41.3 |
39.5 |
36.3 |
56.3 |
Karowe carats sold |
Carats |
116,221 |
76,387 |
93,560 |
111,523 |
111,673 |
|
|
|
|
|
|
|
Production |
|
|
|
|
|
|
Tonnes mined (ore) |
Tonnes |
845,594 |
699,846 |
809,999 |
607,101 |
869,188 |
Tonnes mined (waste) |
Tonnes |
192,308 |
245,006 |
386,849 |
456,880 |
954,226 |
Tonnes processed |
Tonnes |
720,524 |
714,301 |
698,870 |
703,472 |
724,640 |
Average grade processed(1) |
cpht (*) |
13.4 |
12.9 |
11.7 |
14.0 |
13.6 |
Carats recovered(1) |
Carats |
96,597 |
92,419 |
81,611 |
98,177 |
98,311 |
|
|
|
|
|
|
|
Costs |
|
|
|
|
|
|
Operating cost per tonne of ore processed(2) |
US$ |
27.34 |
26.32 |
26.00 |
31.96 |
28.84 |
|
|
|
|
|
|
|
Capital Expenditures |
|
|
|
|
|
|
Sustaining capital expenditures |
US$M |
1.7 |
3.5 |
1.8 |
8.0 |
3.2 |
Underground expansion project(3) |
US$M |
24.1 |
11.2 |
17.9 |
28.0 |
20.3 |
(*) Carats per hundred tonnes |
QUARTERLY SALES RESULTS
|
|
|
|
|
|
|
Three months ended
|
|
Nine months ended
|
||
Revenue is in millions of |
2024 |
2023 |
|
2024 |
2023 |
Sales Channel |
|
|
|
|
|
HB Arrangements |
27.8 |
38.4 |
|
80.6 |
88.8 |
Tender(1) |
14.6 |
14.2 |
|
36.8 |
36.8 |
Clara |
1.9 |
3.7 |
|
7.7 |
10.5 |
Total Revenue |
44.3 |
56.3 |
|
125.1 |
136.1 |
(1) Non-gem +10.8 carat diamonds and diamonds less than 10.8 carats that did not meet characteristics for sale on Clara were sold through tender. |
HB Arrangement
For the three months ended
Quarterly Tender & Clara
For the three months ended
2024 OUTLOOK
This section of the news release provides management's production and cost estimates for the remainder of 2024. These are "forward-looking statements" and subject to the cautionary note regarding the risks associated with forward-looking statements. Diamond revenue guidance does not include revenue related to the sale of exceptional stones (an individual rough diamond which sells for more than
Revisions to diamond revenue guidance reflect lower production of HB qualifying Specials combined with softening of the global rough diamond market during 2024. Revenue is expected to be lower than the initial guidance of
Revisions to Karowe UGP capital costs to be spent in 2024 have been revised down to approximately
|
2024 |
In millions of |
Full Year |
Revised Diamond revenue (millions) |
|
Diamond sales (thousands of carats) |
345 to 375 |
Diamonds recovered (thousands of carats) |
345 to 375 |
Ore tonnes mined (millions) |
2.8 to 3.2 |
Waste tonnes mined (millions) |
0.8 to 1.4 |
Ore tonnes processed (millions) |
2.6 to 2.9 |
Total operating cash costs(1) including waste mined (per tonne processed) |
|
Revised
|
Up to |
Sustaining capital |
Up to |
Average exchange rate – Botswana Pula per United States Dollar |
12.5 |
(1) Operating cash costs are a non-IFRS measure. See "Use of Non-IFRS Performance Measures". |
The table above reflects the natural variability in the resource production in both recovery and diamond quality and were it to continue, this may impact revenue guidance for 2024.
In 2024, the Company expects to mine between 3.6 and 4.6 million tonnes, of which ore tonnes mined represent approximately three quarters of total tonnes mined. The assumptions for carats recovered and sold as well as the number of ore tonnes processed are consistent with achieved plant performance in recent years. A portion of the tonnes mined in 2024 will be stockpiled, prior to the end of open pit mining in mid-2025. Stockpiled material is planned to be processed between 2025 to 2027 before the mine transitions to the underground operations. Ore from the underground development is expected to supplement lower grade stockpile material, primarily from the upper benches of the South lobe, during the transition period to the underground mining operations, beginning in 2027.
Sustaining capital and project expenditures are expected to be up to
On behalf of the Board,
President and Chief Executive Officer
Follow
ABOUT LUCARA
Lucara is a leading independent producer of large exceptional quality Type IIa diamonds from its 100% owned
The information is information that Lucara is obliged to make public pursuant to the EU Market Abuse Regulation. This information was submitted for publication, through the agency of the contact person set out above, on
CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS
Certain of the statements made in this news release contain certain "forward-looking information" and "forward-looking statements" as defined in applicable securities laws. Generally, any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance and often (but not always) using forward-looking terminology such as "expects", "is expected", "anticipates", "believes", "plans", "projects", "estimates", "budgets", "scheduled", "forecasts", "assumes", "intends", "goals", "objectives", "potential", "possible" or variations thereof or stating that certain actions, events, conditions or results "may", "could", "would", "should", "might" or "will" be taken, occur or be achieved, (or the negative of any of these terms and similar expressions) are not statements of historical fact and may be forward-looking statements.
By their nature, forward-looking statements and information involve assumptions, inherent risks and uncertainties, many of which are difficult to predict and are usually beyond the control of management, that could cause actual results to be materially different from those expressed by these forward-looking statements and information. Forward-looking information and statements are based on the opinions and estimates of management as of the date such statements are made, and they are subject to several known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievement expressed or implied by such forward-looking statements. The Company believes that the expectations reflected in this forward-looking information are reasonable, but no assurance can be given that these expectations will prove to be correct. Readers and investors should not place undue reliance on such statements.
This press release contains forward-looking information in several places, such as in statements relating to the Company's ability to continue as a going concern, the project schedule and capital costs for the Karowe UGP, the diamond sales, production and cost estimates under "2024 Outlook", the Company's ability to meet its obligations under the Rebase Amendments with its Lenders, the Company's ability to fill the CORA, the impact of supply and demand of rough or polished diamonds, expectations regarding top-up values, estimated capital costs, the timing, scope and cost of grouting events at the Karowe UGP, that expected cash flow from operations, combined with external financing will be sufficient to complete construction of the Karowe UGP, that the estimated timelines to achieve mine ramp up and full production from the Karowe UGP can be achieved, the economic potential of a mineralized area, expectations that the Karowe UGP will extend mine life, forecasts of additional revenues, future production activity, that depletion and amortization expense on assets will be affected by both the volume of carats recovered in any given period and the reserves that are expected to be recovered, the future price and demand for, and supply of, diamonds, expectations regarding the scheduling of activities for the Karowe UGP in 2024, future forecasts of revenue and variable consideration in determining revenue, the impact of the HB and Clara sales arrangements on the Company's projected revenue and sales channels, the outcome of tax assessments and the likelihood of recoverability of tax payments made, estimation of mineral resources, cost and timing of the development of deposits and estimated future production, interest rates, including expectations regarding the impact of market interest rates on future cash flows and the fair value of derivative financial instructions, and the potential impacts of economic and geopolitical risks.
Certain risks which could impact the Company are discussed under the heading "Risks and Uncertainties" in the Company's most recent MD&A and Annual Information Form available at SEDAR+ at www.sedarplus.ca. Forward-looking information and statements contained in this news release are made as of the date of this news release and accordingly are subject to change after such date. Except as required by law, the Company disclaims any obligation to revise any forward-looking information and statements to reflect events or circumstances after the date of such information and statements. All forward-looking information and statements contained or incorporated by reference in this news release are qualified by the foregoing cautionary statements.
SOURCE