Financial Highlights on a Consolidated Basis include:
-
Constructed assets and construction in progress exceeded
$275 million at quarter end.
- 2025 first quarter consolidated revenues increased 133% as compared to Q1 2024 and 20% as compared to Q4 2024.
-
Net cash used in operating activities was reported at
$5.1 million for the quarter, inclusive of$0.3 million of start-up expenses incurred in anticipation of the commencement of operations of the three new campuses at DVT, ADS and APA and$1.4 million associated with the timing of payment of our accounts payable.
-
Strong liquidity and capital resources as of
March 31 st, 2025, with consolidated cash and US Treasuries totaling$97.4 million .
-
Reiterating our guidance of reaching run rate breakeven operating cash flow/adjusted EBITDA on a consolidated basis by year end 2025, driven by the positive cash flows expected to be generated from the
Phoenix campus partially opened in Q1 2025 and the campuses opening in Q2 inDenver andAddison (Dallas area).
Financial Highlights at
- First quarter 2025 Obligated Group Revenues increased 24% as compared to 2024 Q1.
-
Net cash provided by operating activities reached
$1.0 million in 2025 Q1.
-
Cash and US Treasuries at the
Obligated Group totaled$47 million as ofMarch 30 th, 2025.
Update on Site Acquisition
-
Sky Harbour currently has campuses operating at Houston’sSugar Land Regional Airport (SGR),Nashville International Airport (BNA),Miami Opa-Locka Executive Airport (OPF),San Jose Mineta International Airport (SJC),Camarillo Airport (CMA),Phoenix Deer Valley Airport (DVT), Dallas’sAddison Airport (ADS), and the recent addition of Seattle’sKing County International Airport –Boeing Field (BFI); campus in construction at Denver’sCentennial Airport (APA); campuses in pre-development atChicago Executive Airport (PWK), Sky Harbour’s first fourNew-York -service airports -Bradley International Airport (BDL),Hudson Valley Regional Airport (POU),Trenton-Mercer Airport (TTN),andStewart International Airport (SWF) -Orlando Executive Airport (ORL),Dulles International Airport (IAD),Salt Lake City International Airport (SLC), andPortland-Hillsboro Airport (HIO).
-
On
March 14th , we executed a new ground lease with an existing hangar campus at Seattle’sKing County International Airport –Boeing Field (BFI). The leased facility contains approximately 90,000 rentable square feet of hangar and office space in four structures. We are currently renegotiating tenant lease agreements with the existing tenants and marketing additional vacant space with new prospective tenants.
-
On
April 9 th, we announced a long-term ground lease atHillsboro Airport (HIO) with thePort of Portland to develop a two-phase hangar campus on approximately 13 acres of land.
-
On
April 14 th, we executed a long-term ground lease with thePort Authority of New York and New Jersey (PANYNJ) to develop a hangar campus atStewart International Airport (SWF). The leased parcel encompasses 16 acres and will support the development of approximately 250,000 square feet of hangar space across seven structures.
- We stand by our prior guidance of five additional new hangar ground leases to be announced by the end of 2025, for a total portfolio of 23 airport ground leases by year end.
Update on Construction and Development Activities
- As reported on our monthly activity reports filed with MSRB/EMMA and available on our website, DVT opened for business in Q1 and began operations with the arrival of the first tenant jets. Our campuses at ADS and APA remain forecasted for delivery and commencement of operations during the coming weeks. Please see the following link for the last monthly construction report: https://emma.msrb.org/P11840907-P11410521-P11852991.pdf
-
Phase 2 at OPF started construction on
April 11 th.
Update on Leasing Activities
-
Leasing activity at the Company is at its peak with the recent opening of the campuses in
Phoenix andDallas and the upcoming opening inDenver expected in June. Also, lease up continues at CMA for remaining hangar and just started at the campus at BFI we recently closed on.
-
The first tenant leases were executed in
Phoenix andDallas , with others in negotiation. Pre-leasing continues inDenver , with three new leases under negotiation.
- We continue to expect a 4-6 month lease up period for these three campuses.
Update on Airport Operations
-
Following the hiring of base managers for new locations in
Phoenix ,Dallas andDenver in Q4, hiring and training efforts continued for the remaining team members at each location in Q1. These new hires were onboarded and received training at existing facilities for several weeks prior to their permanent assignments at their new locations, and all locations are now properly staffed.
- Supplies and ground support equipment (GSE), including various aircraft servicing assets and refuelers, were also put into service at the new locations.
About
Forward Looking Statements
Certain statements made in this release are "forward looking statements" within the meaning of the "safe harbor" provisions of the United States Private Securities Litigation Reform Act of 1995, including statements about the financial condition, results of operations, earnings outlook and prospects of SHG, including statements regarding our expectations for future results, our expectations for future ground leases, our expectations on future construction and development activities and lease renewals, and our plans for future financings. When used in this press release, the words “plan,” “believe,” “expect,” “anticipate,” “intend,” “outlook,” “estimate,” “forecast,” “project,” “continue,” “could,” “may,” “might,” “possible,” “potential,” “predict,” “should,” “would” and other similar words and expressions (or the negative versions of such words or expressions) are intended to identify forward-looking statements, but the absence of these words does not mean that a statement is not forward-looking. The forward-looking statements are based on the current expectations of the management of
Key Performance Indicators
We use a number of metrics, including annualized revenue run rate per leased rentable square foot, to help us evaluate our business, measure our performance, identify trends affecting our business, formulate business plans, and make strategic decisions. Our key performance indicators may be calculated in a manner different than similar key performance indicators used by other issuers. These metrics are estimated operating metrics and not projections, nor actual financial results, and are not indicative of current or future performance.
View source version on businesswire.com: https://www.businesswire.com/news/home/20250513505147/en/
Sky Harbour Investor Relations: investors@skyharbour.group Attn:
Source: