Big Upgrades Coming to Akron's East Side Mean Fewer Outages and Faster Restoration
Smart Grid, Stronger Service
Right now, a single problem on any of the five power lines connected to the substation can leave all customers in the dark. But with new technology and equipment, the system will soon be able to detect issues and reroute electricity automatically so that fewer people lose power and those that do, get it back faster.
High-Tech Tools for a Modern Grid
At the heart of the upgrade is gas-insulated switchgear (GIS), a compact high-tech system that safely manages electricity inside sealed, gas-filled enclosures. This setup helps extend equipment life, reduce the risk of outages and keep power flowing more smoothly.
Expanding for the Future
To make room for the new equipment, the substation is expanding from about 142,000 square feet to about 176,000 square feet – roughly equivalent to 37 NBA basketball courts. The expansion is happening entirely on Ohio Edison-owned property, minimizing the impact on the surrounding community.
Construction began in June and is expected to wrap up by the end of 2026. In the meantime, crews are using a temporary setup called a "shoo-fly," a clever workaround that keeps power flowing while the real work gets done. A series of wooden poles and wires acts like a jumper cable to provide temporary power to the substation's 138-kV power line. This allows construction to move forward without interrupting service.
Part of a Bigger Plan
This project is part of Energize365, FirstEnergy's