Q2 2025 HIGHLIGHTS
- In Q2 2025, the Company's revenue increased to
$43.7 million from$41.3 million in Q2 2024, primarily due to the sale of a 1,094 carat diamond (the "Seriti") sold to HB for an initial polished value of$12.0 million . The final sale value of the Seriti will be determined once the polished outcomes are sold to end buyers. - In
July 2025 , the Company recovered a 2,036 carat near-gem diamond. The stone was recovered from processing EM/PK(S)1 kimberlite and is the third largest rough diamond ever unearthed and the second largest rough diamond to be recovered inBotswana . The EM/PK(S) material which is the target of the UGP has now produced seven of the world's largest recorded natural diamond recoveries. - The recovery of 242 Specials (defined as rough diamonds larger than 10.8 carats) (Q2 2024: 206 Specials) equated to 9.4% (Q2 2024: 6.9%) by weight of the total carats recovered from direct ore feed in Q2 2025. During Q2 2025, the Company recovered 15 stones over 100 carats, including two stones that exceeded 200 carats.
- A total of 85,024 carats were recovered in Q2 2025; 82,555 carats were from direct ore feed from the pit and stockpiles, at a recovered grade of 12.5 carats per hundred tonnes ("cpht"), and an additional 2,469 carats were recovered from processing of historical recovery tailings.
- During Q2 2025, the Company successfully funded the Cost Overrun Reserve Account ("CORA") to the required balance of
$61.7 million . Following the funding of the CORA, the lenders approved the withdrawal of$28.0 million from the CORA in exchange for the Company's largest shareholder, Nemesia S.à.r.l. ("Nemesia"), agreeing to extend until project completion its$28.0 million shareholder standby undertaking in support of liquidity shortfalls. - Operational highlights from the
Karowe Mine included: -
- Ore mined of 0.7 million tonnes ("Mt") (Q2 2024: 0.7 Mt).
- 0.7 Mt of ore processed (Q2 2024: 0.7 Mt).
- Financial highlights for Q2 2025 included:
- Operating margins of 65% were achieved, a 2% decrease from operating margins of 67% in Q2 2024. The decrease in operating margins was driven by a 6% increase in revenue and a 12% increase in operating expenses, which reflects the cost of inventory sold during the period.
- Operating cost per tonne processed was
$26.76 per tonne, a 2% increase compared to the Q2 2024 operating cost of$26.32 per tonne. The continued impact of inflationary pressures, particularly labour, has been well managed by the operation. Operating cost per tonne processed is a non-IFRS measure.
- Cash position and liquidity as at
June 30, 2025 :- Cash balance of
$22.7 million . $190.0 million has been fully drawn from the project finance facility ("Project Facility") for the Karowe underground project (the "UGP"), along with$30.0 million fully drawn from the working capital facility ("WCF" and together with the Project Facility, the "Facilities").- Working capital deficit (current assets less current liabilities) of
$156.4 million due to the classification of the Project Facility as a current liability. Refer to discussion under the heading Going Concern for further details. - Excluding the Project Facility from current liabilities, positive working capital balance of
$33.7 million .
- Cash balance of
_______________________ |
1 EM/PK(S): Eastern Magmatic/Pyroclastic Kimberlite (South) |
Progress on the Karowe underground project remains strong, with advancements in shaft sinking, station development, and lateral development as planned. We are delighted to recognize over 2,000 days lost-time injury free on the UGP in July, as well as the completion of the final sinking blast in the production shaft.
As we transition from open-pit to underground operations, we remain focused on disciplined execution and strategic resource management, specifically as we will rely largely on lower-value stockpiled material prior to the UGP coming online. As we navigate this critical transition, we maintain focus on our commitment to recovering maximum value. We recognize that realizing the full potential of our underground resource will involve navigating both the operational and financial complexities ahead."
GOING CONCERN
As of the date of this news release, the Company is completing a review of the UGP ore extraction methodology and is currently updating its geomechanics studies, as well as updating its project cost and schedule. Due to the timing of this review, the Company did not satisfy the requirement to deliver an approved financial model for the UGP to its lenders by
Management has assessed the Company's ability to continue as a going concern for at least twelve months from
The Company continues to develop plans to raise additional financing required for UGP completion. While the Company has previously been successful in raising financing, future fundraising efforts may not succeed or may fall short of the required amounts.
The long-term outlook for natural diamond prices remains cautious as the market continues to navigate structural shifts. Prices of lab-grown diamonds have continued to decrease in 2025 with production outweighing demand. Global natural diamond production is forecasted to decrease, following significant production guidance cuts by the major diamond producers.
In the near term, premium-grade natural diamonds are showing renewed strength, supported by limited global supply growth and strong performance at international trade shows. However, mid-range and lower-grade stones continue to face pricing pressure due to high inventories, cautious consumer sentiment, and the rapid rise of lab-grown diamonds.
Encouraging sign are emerging in the recovery of the Chinese diamond market, which, if remain consistent, will support improved demand dynamics in the quarters ahead.
KAROWE UNDERGROUND PROJECT UPDATE
The UGP is designed to access the highest value portion of the Karowe orebody, with initial underground carat production predominantly from the EM/PK(S) unit.
The Company is currently reviewing its UGP mining ore extraction methodology, project costs and schedule. The UGP has progressed very well including reaching the bottom of the production shaft in late
The mine extraction review does not impact the current UGP development. The Company continues to advance as planned to the lateral development phase of the project. UGP development work continues with equipping the production shaft, commissioning of the shaft conveyances and progressing with its underground infrastructure development near the shafts. Additional lateral development towards the kimberlite is also planned for H2 2025.
During Q2 2025, the UGP achieved a twelve-month rolling Total Recordable Injury Frequency Rate of 0.49. The UGP to date Total Recordable Injury Frequency Rate up to
A total of
Ventilation shaft Q2 2025 developments:
- Completed 335-level station development and sunk towards 310-level.
- Completed the bulk excavation on the top of the Fine Ore Bins.
- Completed 66 metres of lateral development.
Production shaft Q2 2025 developments:
- Completed 285-level station development.
- Continued with the development of the 310-level ramp and 240-level ramp breakaways to the production shaft bottom.
- Completed skip loading pocket excavation and 153 metres of lateral development.
Related infrastructure Q2 2025 developments:
- Continued adjudication and review of underground lateral development tender documents.
- Progressed construction of the Man and Material ("M&M") winder.
- Completed construction of the M&M winder building and winder driver's cabin.
- Continued with rack and cable installations in the M&M winder building.
- Completed construction and lining of the water management pond and commissioned the water blending circuit.
- Advanced mining engineering, focusing on underground infrastructure and finalizing drilling level plans.
Activities planned for the UGP in Q3 2025 include the following:
Ventilation shaft:
- Continue with the 310-level station development.
- Lateral development to connect with the production shaft.
- Commence sinking to 285-level.
Production shaft:
- Complete 285-level station civils and 245-level station development.
- Continue with sink to shaft bottom at the 245-level and commence shaft equipping preparations.
- Strip headgear sinking arrangements.
___________________ |
2 Each level is equivalent to a metre above sea level. |
FINANCIAL HIGHLIGHTS – Q2 2025
|
|
Three months ended |
Six months ended |
||
In millions of |
|
2025 |
2024 |
2025 |
2024 |
|
|
|
|
|
|
Revenues |
|
$ 43.7 |
$ 41.3 |
$ 74.0 |
$ 80.8 |
Operating expenses |
|
(15.4) |
(13.7) |
(29.4) |
(32.0) |
Net income from continuing operations |
|
12.5 |
11.9 |
12.4 |
5.0 |
Net loss from discontinued operations |
|
- |
(0.6) |
- |
(1.5) |
Earnings per share from continuing operations (basic and diluted) |
|
0.03 |
0.03 |
0.03 |
0.01 |
|
|
|
|
|
|
Cash |
|
|
|
22.7 |
21.9 |
CORA |
|
|
|
33.7 |
37.5 |
Amounts drawn on WCF |
|
|
|
30.0 |
25.0 |
Amounts drawn on Project Facility |
|
|
|
$ 190.0 |
$ 165.0 |
|
|
|
|
|
|
Carats sold |
|
77,167 |
76,387 |
150,038 |
169,948 |
QUARTERLY SALES RESULTS
|
Three months ended |
|
Six months ended |
||
In millions of |
2025 |
2024 |
|
2025 |
2024 |
Sales Channel |
|
|
|
|
|
HB |
$ 34.0 |
$ 29.5 |
|
$ 53.2 |
$ 52.8 |
Tender |
1.9 |
2.6 |
|
3.7 |
5.8 |
Clara |
7.8 |
9.2 |
|
17.1 |
22.2 |
Total Revenue |
$ 43.7 |
$ 41.3 |
|
$ 74.0 |
$ 80.8 |
For the three months ended
For the three months ended
QUARTERLY RESULTS FROM OPERATIONS – KAROWE MINE
|
|
Q2-25 |
Q1-25 |
Q4-24 |
Q3-24 |
Q2-24 |
Sales |
|
|
|
|
|
|
Revenues |
$M |
43.7 |
30.3 |
78.8 |
44.3 |
41.3 |
Carats sold |
Carats |
77,167 |
72,871 |
112,615 |
116,221 |
76,387 |
|
|
|
|
|
|
|
Production |
|
|
|
|
|
|
Tonnes mined (ore) |
Tonnes |
721,111 |
390,539 |
646,288 |
845,594 |
699,846 |
Tonnes mined (waste) |
Tonnes |
55,221 |
35,288 |
119,919 |
192,308 |
245,006 |
Tonnes processed |
Tonnes |
661,352 |
676,626 |
716,936 |
720,524 |
714,301 |
Average grade processed(1) |
cpht (*) |
12.5 |
13.4 |
12.7 |
13.4 |
12.9 |
Carats recovered(1) |
Carats |
82,555 |
90,500 |
91,046 |
96,597 |
92,419 |
|
|
|
|
|
|
|
Costs |
|
|
|
|
|
|
Operating cost per tonne of ore processed |
$ |
26.76 |
23.41 |
31.52 |
27.34 |
26.32 |
|
|
|
|
|
|
|
Capital Expenditures |
|
|
|
|
|
|
Sustaining capital expenditures |
$M |
2.0 |
0.5 |
5.5 |
2.0 |
3.45 |
Underground project(3) |
$M |
13.6 |
19.2 |
17.8 |
17.7 |
11.2 |
(*) Carats per hundred tonnes |
||||||
(1) Average grade processed and carats recovered are from direct processing and excludes carats recovered from re-processing historical recovery tailings. |
||||||
(2) Excludes qualifying borrowing cost capitalized. |
2025 OUTLOOK
This section of the news release provides management's production and cost estimates for 2025. These are "forward-looking statements" and subject to the cautionary note regarding the risks associated with such statements.
In Q1 2025, diamond revenue, diamond sales, and diamonds recovered from the 2025 guidance news release dated
|
Revised 2025 |
2025 |
|
In millions of |
Full Year |
Full Year |
|
Revised Diamond revenue (millions) |
|
|
|
Revised Diamond sales (thousands of carats) |
340 to 370 |
400 to 420 |
|
Revised Diamonds recovered (thousands of carats) |
330 to 360 |
360 to 400 |
|
Ore tonnes mined (millions) |
1.6 to 2.0 |
1.6 to 2.0 |
|
Waste tonnes mined (millions) |
Up to 0.2 |
Up to 0.2 |
|
Ore tonnes processed (millions) |
2.6 to 2.9 |
2.6 to 2.9 |
|
Total operating costs(1) including waste mined (per tonne processed) |
|
|
|
Revised Underground Project |
Up to |
Up to |
|
Sustaining capital |
Up to |
Up to |
|
Average exchange rate – Botswana Pula per United States Dollar |
13.0 |
13.0 |
|
(1) Operating cash costs are a non-IFRS measure. See "Non-IFRS Measures". |
The table above reflects the natural variability in the resource, including both recovered grade and diamond quality, which may influence the revenue guidance for 2025.
In 2025, the Company expects to mine between 1.8 and 2.2 million ore tonnes including waste. Mined ore will be processed in combination with stockpiled material in 2025. The assumptions for carats recovered and sold as well as the number of ore tonnes processed are consistent with achieved plant performance in recent years. Stockpiled material (North, Centre, South Lobe) from working stockpiles and life-of-mine stockpiles should provide mill feed until 2027 when UGP development ore is scheduled to start offsetting stockpiles with high-grade ore from the UGP. Full scale underground production is planned for H1 2028.
In 2025, capital costs for the UGP are expected to be up to
Sustaining capital is expected to be up to
On behalf of the Board,
President and Chief Executive Officer
Follow Lucara Diamond on Facebook, Instagram and LinkedIn
___________________ |
3 M/PK(S): Magmatic/Pyroclastic Kimberlite (South) |
ABOUT LUCARA
Lucara is a leading independent producer of large exceptional quality Type IIa diamonds from its 100% owned
The information in this release is subject to the disclosure requirements of Lucara pursuant to the EU Market Abuse Regulation. The Company's certified adviser on the Nasdaq First North Growth Market is
CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS
Certain statements made in this news release contain "forward-looking information" and "forward-looking statements" as defined in applicable securities laws. Generally, any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance and often (but not always) using forward-looking terminology such as "expects", "is expected", "anticipates", "believes", "plans", "projects", "estimates", "budgets", "scheduled", "forecasts", "assumes", "intends", "strategy", "goals", "objectives", "potential", "possible" or variations thereof or stating that certain actions, events, conditions or results "may", "could", "would", "should", "might" or "will" be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and may be forward-looking statements.
Forward-looking information and forward-looking statements may include, but are not limited to, information or statements with respect to the Company's ability to continue as a going concern, the Company's ability to continue operations, realize assets, and settle its liabilities as they become due, the project schedule and capital costs for the UGP, diamond sales, projection and outlook disclosure under "2025 Outlook", the Company's ability to meet its obligations under the Rebase Amendments with its Lenders, the impact of supply and demand of rough or polished diamonds, estimated capital costs, future forecasts of revenue and variable consideration in determining revenue, the impact of the HB and Clara sales arrangements on the Company's projected revenue and sales channels and HB's ability to meet its payment obligations to the Company, the outcome of tax assessments and the likelihood of recoverability of tax payments made, estimation of mineral resources including the determination of the boundary between South Lobe M/PK(S) and EM/PK(S) domains due to the significant grade difference between these two domains, cost and timing of the development of deposits and estimated future production, interest rates, including expectations regarding the impact of market interest rates on future cash flows and the fair value of derivative financial instruments, currency exchange rates, rates of inflation, credit risk, price risk, requirements for and availability of additional capital, capital expenditures, operating costs, production and cost estimates, tax rates, timing of drill programs, government regulation of operations, environmental risks and the Company's ability to comply with all environmental regulations, reclamation expenses, title matters including disputes or claims, limitations on insurance coverage, and the potential impacts of economic and geopolitical risks, including potential impacts from the ongoing world conflicts, and the resulting indirect economic impacts that strict economic sanctions may have. While these factors and assumptions are considered reasonable by the Company as at the date of this news release in light of management's experience and perception of current conditions and expected developments, these statements are inherently subject to significant business, economic and competitive uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those projected in the forward-looking information and undue reliance should not be placed on such information. Such factors include, but are not limited to: the timing, scope and cost of additional grouting events at the UGP, the Company's ability to comply with the terms of the Facilities which are required to construct the UGP, the impact of the Non-Financial Covenant Breaches, and any associated consequences, on the Company's business, whether the Lenders will demand payment of the Facilities because of the Non-Financial Covenant Breaches, that expected cash flow from operations, combined with external financing will be sufficient to complete construction of the UGP, that the estimated timelines to achieve mine ramp up and full production from the UGP can be achieved, that sufficient stockpiled ore of sufficient grade and value will be available to generate revenue prior to the achievement of commercial production of the Karowe underground mine, the economic potential of a mineralized area, the size and tonnage of a mineralized area, anticipated sample grades or bulk sample diamond content, expectations that the UGP and the pit steepening project will extend mine life, forecasts of additional revenues, future production activity, that depletion and amortization expense on assets will be affected by both the volume of carats recovered in any given period and the reserves that are expected to be recovered, the future price and demand for, and supply of, diamonds, expectations regarding the scheduling of activities for the UGP.
Forward-looking information and statements are based on the opinions and estimates of management as of the date such statements are made, and they are subject to several known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievement expressed or implied by such forward-looking statements due to a variety of risks, uncertainties, and other factors, including, without limitation, those referred to in this news release. The foregoing is not exhaustive of the factors that may affect any of our forward-looking statements. The Company believes that expectations reflected in this forward-looking information are reasonable, but no assurance can be given that these expectations will prove to be correct. Certain risks which could impact the Company are discussed under the heading "Risks and Uncertainties" in the Company's most recent MD&A and in the Company's most recent Annual Information Form available at SEDAR+ at www.sedarplus.ca.
Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. Accordingly, readers and investors should not place undue reliance on forward-looking statements. Forward-looking information and statements contained in this news release are made as of the date of this news release and accordingly are subject to change after such date. Except as required by law, the Company disclaims any obligation to revise any forward-looking information and statements to reflect events or circumstances after the date of such information and statements. All forward-looking information and statements contained or incorporated by reference in this news release are qualified by the foregoing cautionary statements.
SOURCE