Lithium Americas Reports Second Quarter 2025 Results
(All amounts in US$ unless otherwise indicated)
“Thacker Pass is undergoing noticeable growth every week, and we now have over 300 workers on site. The processing plant area is materializing with the placement of permanent concrete foundations and facility entrances, and building of permanent roads is underway throughout the site. The first shipment of steel arrived in
Q2 2025 PROJECT AND CONSTRUCTION HIGHLIGHTS
-
On
April 1, 2025 , the Company andGeneral Motors Holdings LLC ("GM ") (together, the "Joint Venture (JV) Partners ") announced the final investment decision (“FID”) for construction of Phase 1 ofThacker Pass . -
During the quarter ended
June 30, 2025 ,$124.8 million of construction capital costs and other project-related costs were capitalized. As ofJune 30, 2025 , a total of$574.1 million of construction capital costs and other project-related costs have been capitalized. -
The Company has resolved or secured judicial dismissal of all legal and regulatory actions and proceedings, which arose in the ordinary course of resource development. Those resolutions did not materially impact the Company’s financial position or construction schedule. The Company continues to progress major construction at
Thacker Pass . Completion of Phase 1 ofThacker Pass is targeted for late 2027. -
Project engineering and procurement continue materially in line with the Project schedule to support construction.
-
As of
June 30, 2025 , detailed engineering is approximately 70% design complete and expected to increase to over 90% design complete by year end 2025. The higher level of detailed engineering at the early stages of construction helps to de-risk execution in terms of Project schedule and cost. -
In
April 2025 , fabrication of the structural steel to be used to build the facilities atThacker Pass commenced. First steel installation is targeted to commence inSeptember 2025 . -
Manufacturing of long-lead equipment continues to advance with expected delivery in line with the Project schedule.
-
The Company has entered into certain long-term purchase agreements related to long-lead equipment, infrastructure and services related to the construction of the processing plant as well as development and mining services at
Thacker Pass . To date, approximately$425 million has been committed.
-
As of
-
Major construction at
Thacker Pass is progressing, with permanent concrete placement in the processing plant area commencing in earlyMay 2025 . Activity at site is focused on key areas to enable peak construction, which is expected in 2026. As ofJune 30, 2025 :-
There were approximately 300 manual craft workers on site, which is expected to increase to approximately 1,000 workers by year end 2025. At peak construction, approximately 1,800 workers are expected on site.
-
Structural excavation was underway to support the buildout of facilities and structural elements such as pipe racks.
-
Foundation preparation and rebar for concrete for the processing plant facilities continued to progress.
-
Construction of permanent roads and entrances to the processing plant facilities were underway.
-
Worker break tents were nearing completion.
-
There were approximately 300 manual craft workers on site, which is expected to increase to approximately 1,000 workers by year end 2025. At peak construction, approximately 1,800 workers are expected on site.
-
Placement of housing modules at the Company’s all-inclusive housing facility for construction workers in
Winnemucca (the “Workforce Hub” or “WFH”) is well advanced. Mechanical, electrical and plumbing work is progressing, with first occupancy targeted for the second half of 2025. The completion of the WFH will enable ramp-up in the number of construction workers at site.
Q2 2025 FINANCIAL AND CORPORATE HIGHLIGHTS
-
As of
June 30, 2025 , the Company had$509.1 million in cash and restricted cash.-
On
April 1, 2025 , the Company closed the previously announced strategic investment from fund entities managed byOrion Resource Partners LP (collectively, “Orion”), for the development and construction of Phase 1 ofThacker Pass (“Orion Investment ”). As part of closing, Orion paid the Company total gross proceeds of$220 million in cash for$195 million of senior unsecured convertible notes (the “Notes”) and$25 million in exchange for payments corresponding to the minerals produced and gross revenue generated byThacker Pass (the “Production Payment Agreement” or “PPA”). -
On declaring FID,
GM and the Company contributed$100 million and$191.6 million in cash to the JV, respectively.
-
On
-
On
May 15, 2025 , the Company established an at-the-market equity program (“ATM Program”) pursuant to which the Company may sell its common shares, no par value, for up to a maximum aggregate$100 million and intends to use the net proceeds for general corporate purposes, which may include funding of corporate and project overhead expenses, financing of capital expenditures, repayment of indebtedness and additions to working capital.-
As of
June 30, 2025 , the Company issued and sold 3.361 million common shares at an average price of$2.76 per share pursuant to the ATM Program, for aggregate net proceeds of$8.5 million after sales agent’s commission and other expenses. Subsequent toJune 30, 2025 , the Company issued and sold 18.103 million common shares at an average price of$3.11 per share pursuant to the ATM Program, for aggregate net proceeds of$55.1 million after sales agent’s commission and other expenses.
-
As of
-
The Company currently expects to make the first draw on the previously announced
$2.26 billion loan from theDepartment of Energy (“DOE ” / the “DOE Loan”) sometime in the second half of 2025.-
In advance of first draw,
GM has released to the Company the previously announced$195 million letter of credit facility that can be used as collateral to support reserve account requirements under the DOE Loan.
-
In advance of first draw,
-
On
July 29, 2025 , the Company published an environment, social, governance and safety (“ESG-S”) report, themed “Driving Partnerships to Create Value,” available on the Company’s website. The report includes sustainability performance and progress activities for the periodJanuary 1 to December 31, 2024 at the corporate level,Thacker Pass , WFH,Lithium Technical Development Center and the Company’s office locations.
FINANCIALS
Selected consolidated financial information is presented as follows:
(in US$ million except per share information) |
|
Six months ended |
|
|||||
|
|
2025 |
|
|
2024 |
|
||
|
|
$ |
|
|
$ |
|
||
Operating expenses |
|
|
14.4 |
|
|
|
12.2 |
|
Net loss |
|
|
24.8 |
|
|
|
12.8 |
|
Loss per share - basic |
|
|
0.11 |
|
|
|
0.07 |
|
(in US$ millions) |
|
As at |
|
|
As at |
|
||
|
|
$ |
|
|
$ |
|
||
Cash and restricted cash |
|
|
509.1 |
|
|
|
594.2 |
|
Total assets |
|
|
1,339.1 |
|
|
|
1,044.9 |
|
Total long-term liabilities |
|
|
251.5 |
|
|
|
41.3 |
|
During the six months ended
At
This news release should be read in conjunction with the Company’s Quarterly Report on Form 10-Q for the three and six months ended
ABOUT
TECHNICAL INFORMATION
The scientific and technical information in this news release has been reviewed and approved by
FORWARD-LOOKING STATEMENTS
This news release contains “forward-looking information” within the meaning of applicable Canadian securities legislation, and “forward-looking statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995 (collectively referred to as “forward-looking statements” or “FLS”). All statements, other than statements of historical fact, are FLS and can be identified by the use of statements that include, but are not limited to, words, such as “anticipate,” “plan,” “continue,” “estimate,” “expect,” “may,” “will,” “project,” “predict,” “propose,” “potential,” “target,” “implement,” “schedule,” “forecast,” “intend,” “would,” “could,” “might,” “should,” “believe” and similar terminology, or statements that certain actions, events or results “may,” “could,” “would,” “might” or “will” be taken, occur or be achieved. FLS in this news release includes, but is not limited to: statements relating to the anticipated sources and uses of funds to complete project financing, statements relating to the JV, the DOE Loan and the
FLS involves known and unknown risks, assumptions and other factors that may cause actual results or performance to differ materially. FLS reflects the Company’s current views about future events, and while considered reasonable by the Company as of the date of this news release, are inherently subject to significant uncertainties and contingencies. Accordingly, there can be no certainty that they will accurately reflect actual results. Assumptions and other factors upon which such FLS is based include, without limitation: expectations regarding Phase 2 of
Readers are cautioned that the foregoing lists of factors are not exhaustive. There can be no assurance that FLS will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. As such, readers are cautioned not to place undue reliance on this information, and that this information may not be appropriate for any other purpose, including investment purposes. The Company’s actual results could differ materially from those anticipated in any FLS as a result of the risk factors set out herein, and in the Company’s other continuous disclosure documents available on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov. Readers are further cautioned to review the full description of risks, uncertainties and management’s assumptions in the aforementioned documents and other disclosure documents available on SEDAR+ and on EDGAR.
The Company expressly disclaims any obligation to update FLS as a result of new information, future events or otherwise, except as and to the extent required by applicable securities laws. Forward-looking financial information also constitutes FLS within the context of applicable securities laws and as such, is subject to the same risks, uncertainties and assumptions as are set out in the cautionary note above.
View source version on businesswire.com: https://www.businesswire.com/news/home/20250814656448/en/
INVESTOR CONTACT
+1-778-726-4070
ir@lithiumamericas.com
Source: