Woodside Energy releases 2025 half-year results
HALF-YEAR REPORT FOR PERIOD ENDED
Strong global portfolio delivers value and growth
Strong first half performance
- Determined a fully franked interim dividend of 53 US cents per share (cps).
-
Delivered production of 548 Mboe/d (99.2 MMboe) and reduced unit production costs to
$7.7 /boe.1 -
Achieved strong progress on major projects with
Scarborough 86%, Trion 35%, and Beaumont New Ammonia 95% complete. -
Positioned to unlock future value through the final investment decision (FID) to develop the
Louisiana LNG Project . -
Completed the sell-down of a 40% interest in
Louisiana LNG Infrastructure LLC to Stonepeak. - On track to meet Woodside’s net equity Scope 1 and 2 greenhouse gas emissions reduction target of 15% by 2025.2
Achieving operational excellence
- Recorded over one million work hours in Sangomar’s first year with no recordable injuries.
- Maintained exceptional performance from Sangomar with 100 Mbbl/d produced (100% basis, 80 Mbbl/d Woodside share).
- Achieved strong operated LNG plant performance with combined reliability of 96%.
- Contributed approximately 8% of EBIT from our marketing and trading capability.
Strong financial outcomes and capital discipline
-
Achieved net profit after tax of
$1,316 million . -
Delivered strong EBITDA of
$4,600 million from underlying base business.1 -
Delivered operating cash flow of
$3,339 million . -
Disciplined capital management resulted in strong liquidity of
$8,430 million and gearing of 19.5%, within the target range.1 -
Issued
$3,500 million of senior unsecured bonds in the US market, with the book heavily oversubscribed.
Comparative performance |
||||||
|
|
H1
|
H1
|
Change
|
|
|
Operating revenue |
$ million |
6,590 |
5,988 |
10% |
|
|
Underlying NPAT1 |
$ million |
1,247 |
1,632 |
(24%) |
|
|
Free cash flow1,3 |
$ million |
272 |
740 |
(63%) |
|
|
Average realised price1 |
US$/boe |
61.8 |
62.6 |
(1%) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2025 full-year guidance |
|
|
|
|
|
|
Prior |
Current |
Production4 |
MMboe |
99.2 |
89.3 |
11% |
186 - 196 |
188 - 195 |
Gas hub exposure5 |
% of produced LNG |
24.2% |
34.0% |
(9.8%) |
28 - 35 |
No change |
Unit production cost1 |
$/boe |
7.7 |
8.3 |
(7%) |
8.5 - 9.2 |
8.0 - 8.5 |
Property, plant and equipment depreciation and amortisation |
$ million |
2,541 |
1,893 |
34% |
4,500 - 5,000 |
4,700 - 5,000 |
Exploration expenditure1 |
$ million |
86 |
112 |
(23%) |
200 |
No change |
Payments for restoration |
$ million |
565 |
325 |
74% |
700 - 1,000 |
No change |
Capital expenditure (excluding Louisiana LNG)1 |
$ million |
1,773 |
2,365 |
(25%) |
4,500 - 5,000 |
4,000 - 4,500 |
Net capital expenditure on Louisiana LNG1,6 |
$ million |
785 |
— |
— |
|
|
This page and the following 65 pages comprise the half year end information given to the ASX under Listing Rule 4.2A and should be read in conjunction with Woodside’s Annual Report 2024. |
Summary |
Woodside delivered strong half-year production of 548 thousand barrels oil equivalent per day (99.2 million barrels of oil equivalent total) and reported a half-year net profit after tax (NPAT) of
The directors have determined a fully franked interim dividend of 53 US cents per share (cps), representing an 80% payout ratio of underlying NPAT, and an annualised yield of 6.9%.7
CEO
“Strong underlying performance of our assets, our robust financial performance, and a focus on disciplined capital management have enabled us to maintain our interim dividend payout ratio at the top end of the payout range.
“The outstanding performance of our high-quality assets over the first half has continued to support safe, reliable operations. This has been complemented by a strong focus on cost management, resulting in a reduction in our unit production costs. We have also taken a disciplined approach to future growth and reduced spend on new energy and exploration as we prioritise delivering sanctioned projects.
“A highlight was the ongoing exceptional performance of our
“Our excellence in project delivery was further demonstrated in the first half.
“In April we took a final investment decision on Louisiana LNG, positioning Woodside as a global LNG powerhouse able to meet growing customer demand in the Pacific and Atlantic Basins. The Project’s compelling value proposition was reinforced with key infrastructure, offtake, and gas supply agreements signed with high-quality partners. This included completion of the sell-down of a 40% interest in
“We continue to receive strong interest from high-quality potential partners as we explore further sell-downs of Louisiana LNG. This highlights the distinct value Woodside offers, with our business model well positioned to deliver compelling long-term value in the US LNG market, further differentiated by our extensive LNG experience, portfolio marketing capabilities, and balance sheet strength.
“Further strengthening our operational capabilities and subsequent to the period, we agreed to assume operatorship of the
“Safety remains at the forefront of everything we do. We marked significant safety milestones across our global portfolio over the period including 100,000 hours worked across two major turnarounds at the
Financial summary |
Key metrics |
||||
|
|
H1 |
H1 |
Change |
|
|
2025 |
2024 |
% |
Operating revenue |
$ million |
6,590 |
5,988 |
10% |
EBITDA excluding impairment8 |
$ million |
4,600 |
4,371 |
5% |
EBIT8 |
$ million |
1,817 |
2,362 |
(23%) |
Net profit after tax (NPAT)910 |
$ million |
1,316 |
1,937 |
(32%) |
Underlying NPAT8 |
$ million |
1,247 |
1,632 |
(24%) |
Net cash from operating activities |
$ million |
3,339 |
2,393 |
40% |
Capital expenditure8,11 |
$ million |
2,558 |
2,365 |
8% |
Exploration expenditure8,12 |
$ million |
86 |
112 |
(23%) |
Free cash flow8,13 |
$ million |
272 |
740 |
(63%) |
Average realised price8 |
US$/boe |
61.8 |
62.6 |
(1%) |
Dividends distributed |
$ million |
1,006 |
1,310 |
(23%) |
Interim dividend declared |
US cps |
53 |
69 |
(23%) |
|
|
|
|
|
Key ratios |
|
|
|
|
Earnings |
US cps |
69.4 |
102.2 |
(32%) |
Gearing8 |
% |
19.5 |
13.3 |
6.2% |
|
|
|
|
|
Production volumes1415 |
|
|
|
|
Gas |
MMboe |
58.2 |
60.9 |
(4%) |
Liquids |
MMboe |
41.0 |
28.4 |
44% |
Total |
MMboe |
99.2 |
89.3 |
11% |
|
|
|
|
|
Production volumes per day15 |
|
|
|
|
Gas |
MMscf/d |
1,833 |
1,907 |
(4%) |
Liquids |
Mbbl/d |
226 |
156 |
45% |
Total |
Mboe/d |
548 |
491 |
12% |
|
|
|
|
|
Sales volumes15 |
|
|
|
|
Gas16 |
MMboe |
63.7 |
64.9 |
(2%) |
Liquids |
MMboe |
40.9 |
28.9 |
42% |
Total |
MMboe |
104.6 |
93.8 |
12% |
|
|
|
|
|
Sales volumes per day15 |
|
|
|
|
Gas16 |
MMscf/d |
2,006 |
2,032 |
(1%) |
Liquids |
Mbbl/d |
226 |
159 |
42% |
Total |
Mboe/d |
578 |
516 |
12% |
Appendix 4D |
Results for announcement to the market |
||||
More information is available on page 49. |
||||
|
|
|
|
US$ million |
Revenue from ordinary activities |
Increased |
10%17 |
to |
6,590 |
Profit from ordinary activities after tax attributable to members |
Decreased |
32%17 |
to |
1,316 |
Net profit for the period attributable to members |
Decreased |
32%17 |
to |
1,316 |
|
|
|
|
|
Interim dividend - fully franked |
|
53 US cps H1 2025 |
|
|
Record date for determining entitlements to the dividend |
|
|
|
Net profit after tax reconciliation |
The following table summarises the variance between the H1 2024 and H1 2025 results for the contribution of each line item to NPAT. |
||
|
US$m |
Primary reasons for variance |
2024 H1 reported NPAT |
1,937 |
|
Revenue from sale of hydrocarbons |
|
|
Price |
(154) |
Lower average realised prices. |
Volume |
754 |
Full period of Sangomar production primarily offset by NWS and Pluto production. |
Cost of sales |
(773) |
Full period of Sangomar production costs, depreciation and amortisation. |
Perdaman embedded derivative |
315 |
Remeasurement of the Perdaman embedded derivative at fair value and accretion on contract liability. |
|
(121) |
Profit on 10% |
Restoration movement |
(430) |
Restoration provision updates primarily due to Stybarrow, Griffin and Minerva. |
Impairment losses |
(143) |
Pre-tax impairment on the |
Income tax and PRRT expense |
(86) |
Recognition of the Sangomar deferred tax asset (DTA) in 2024 offset by recognition of the Louisiana LNG DTA in 2025. |
Other |
17 |
|
2025 H1 reported NPAT |
1,316 |
|
2025 H1 NPAT adjustments |
(69) |
Adjusted for the recognition of the Louisiana LNG DTA and the post-tax impairment on the |
2025 H1 underlying NPAT |
1,247 |
|
Capital management |
Woodside’s capital management framework provides us with the flexibility to optimise value and shareholder returns delivered from our portfolio of opportunities.
Interim dividend and dividend reinvestment plan
A 2025 fully franked interim dividend of 53 US cps has been determined, representing an annualised dividend yield of 6.9%.18 The total amount of the interim dividend payment is
The dividend reinvestment plan remains suspended.
Liquidity and balance sheet
In H1 2025, Woodside generated
During this period, Woodside undertook the following financing activities:
-
Raised
$3,500 million in the US market through a multi-trancheSEC -registered bonds issue inMay 2025 , consisting of$500 million three-year bonds,$1,250 million five-year bonds,$500 million seven-year bonds, and$1,250 million ten-year bonds. -
Refinanced
$1,200 million of syndicated revolving facilities, with$600 million now maturing inJune 2028 and the remaining$600 million inJune 2030 . -
Repaid a
$1,000 million ten-year US bond that matured.
At the end of the period, Woodside had cash and cash equivalents of
Woodside’s gearing at the end of the first half was 19.5%, within our target range of 10 to 20%.19 Woodside’s gearing may at times fall outside this target range as the balance sheet is managed through the investment cycle.
Woodside’s commitment to an investment-grade credit rating remains unchanged and supports our aim of providing sustainable returns to shareholders, both now from our strong existing business and in the future from our growth opportunities, in accordance with Woodside’s capital allocation framework.
Commodity price risk management
As at
-
Approximately 30 MMboe of 2025 production at an average price of
$78.7 per barrel, of which approximately 58% has been delivered.
-
A total of 10 MMboe of 2026 production at an average price of approximately
$70.1 per barrel.
Woodside has also placed a number of hedges for Corpus Christi LNG volumes. These hedges are
Embedded commodity derivative
In 2023, Woodside entered a revised long-term gas sale and purchase agreement with Perdaman. A component of the selling price is linked to the price of urea, creating an embedded commodity derivative in the contract. The fair value of the embedded derivative is estimated using a Monte Carlo simulation model.
During the period, Woodside reassessed the embedded derivative calculation to factor in current market conditions and pricing inputs that reflect the long-term nature of the contract and associated market. Updates to the valuation model inputs include:
- 30-day average pricing assumptions and longer-term external pricing forecasts to reflect the long-term nature of the contract; and
- longer-term historical data excluding extreme volatility periods, to reflect typical market conditions.
As there is no long-term urea forward curve, TTF continues to be used as a proxy to simulate the value of the derivative over the life of the contract. For the half-year ended
Australian operations |
Woodside’s share of production in H1 2025 was 25.5 MMboe. This was a 5.2% decrease compared with H1 2024 due to unplanned outages. This decrease was partially offset by production through the Pluto-Karratha Gas Plant Interconnector, with 5.6 MMboe of Pluto production processed at Karratha Gas Plant through the
In H1 2025, production from the PLA-08 well commenced, enhancing deliverability and extending plateau production. Woodside also secured secondary environmental approval enabling development of the XNA-03 well through existing infrastructure to support sustained production.
Woodside is operator and holds a 90% participating interest.
Woodside is progressing a potential opportunity to reduce gross Scope 1 greenhouse gas emissions at
Woodside Solar final investment decision and first solar energy import timing depend on securing access to proposed new common-user transmission infrastructure that will be required to transmit renewable energy to
Woodside’s share of production in H1 2025 was 15.1 MMboe. This was a 23.0% decrease compared with H1 2024 due to reservoir decline, planned maintenance at the Goodwyn Alpha platform, and cyclone activity.
In H1 2025, the NWS Joint Venture participants approved long lead items for the Greater Western Flank Phase 4 Project, a five-well subsea tie-back to existing NWS offshore facilities, with final investment decision targeted for the second half of 2025.
After 40 years of operations, the NWS is entering a period of production decline. KGP will progressively have increased processing ullage due to natural field decline, despite the ongoing processing of third-party gas. To optimise operations, the NWS permanently retired LNG Train 2 in H1 2025. This retirement resulted in a reduction of KGP’s production capacity from 16.9 Mtpa to 14.3 Mtpa.
Subsequent to the period, the Lambert West development well was successfully drilled, subsea infrastructure was installed and startup commenced. The Project will sustain production from the Angel Platform.
The regulatory approval processes continued to progress for the NWS Project Extension, which will support long-term operations and processing of future third-party gas resources at KGP. A proposed approval was issued by the Australian Government on the NWS Project Extension. Woodside and the NWS Joint Venture are continuing to consult with the Australian Government and assess the proposed conditions as part of the proposed approval.
Woodside is operator and holds a 33.33% participating interest.
Following completion of the asset swap agreement with
Wheatstone and Julimar-Brunello
Wheatstone is an LNG processing facility near
Woodside’s share of Wheatstone production in H1 2025 was 6.3 MMboe. This was a 8.6% increase compared with H1 2024 due to higher reliability.
The Julimar Phase 3 Project is a four-well tie-back to the existing Julimar field production system. Subsea construction began during the half, and subsequent to the period the drilling campaign commenced. The Project is expected to startup in 2026.
Woodside is operator and holds a 65% participating interest in the Julimar-Brunello fields.
Woodside holds a 13% non-operating participating interest in the
Following completion of the asset swap agreement with
Woodside’s share of production from
In H1 2025, Woodside approved investment in the Kipper 1B Project and the Turrum Phase 3 Project. Through these Projects, Woodside is expected to add more than 100 PJ of gas (Woodside share) to the south eastern Australian domestic gas market.
Subsequent to the period, Woodside agreed to assume operatorship of the
Woodside holds a 50% non-operating participating interest in the GBJV and a 32.5% non-operating participating interest in the KUJV. Upon completion of the agreement with ExxonMobil, Woodside will become operator, but there will be no change to Woodside’s participating interests.
Other Australian oil and gas assets
Woodside operates three floating production storage and offtake (FPSO) facilities off the north west coast of
Following completion of the asset swap agreement with
Woodside’s share of production from the FPSO assets was 3.6 MMboe in H1 2025. This was a 20.0% increase from H1 2024 primarily due to the planned five-yearly Pyrenees FPSO maintenance turnaround in H1 2024 and the Pyrenees shut-in following a subsea produced-water leak at the facility in H1 2024.
Macedon (Woodside participating interest: 71.4%), also operated by Woodside, is a gas project located near
Woodside’s share of production from Macedon was 4.2 MMboe, a 7.7% increase from H1 2024 driven by reservoir performance and strong demand. The Macedon facility delivered approximately 16% of the Western Australian domestic gas market supply in H1 2025.
International operations |
Sangomar
The Sangomar Field Development Phase 1 is a deepwater project including a stand-alone FPSO facility moored approximately 100 km offshore
Woodside’s share of production was 14.4 MMboe in H1 2025. First oil was achieved in
In H1 2025, Sangomar achieved exceptional production, averaging 100 Mbbl/d (100% basis, 80 Mbbl/d Woodside share) at 98.6% reliability, with production from the field remaining at plateau for the half-year. The field is expected to come off plateau in Q3 2025.
Based on a positive response observed in the S400 oil producer wells from water injection, contingent resources were migrated to developed reserves during the period. The reserve addition was 7.1 million barrels to proved (1P) reserves and 16.1 million barrels to proved plus probable (2P) reserves, Woodside share. Subsequent to the period, strong field performance in the S500 reservoirs resulted in an additional 18.4 million barrels of proved (1P) reserves being added.25 As a result, Woodside expects Sangomar's depreciation, depletion and amortisation (DD&A) rate to further reduce in the second half of 2025.
Sales of the initial Sangomar crude cargoes are receiving strong interest from European, North American and Asian refiners. As at
Woodside has filed an action with the
Woodside is operator and has an 82% participating interest in the Project.
Shenzi
Shenzi is a conventional offshore oil and gas field developed through a tension leg platform located in
Woodside’s share of production in H1 2025 was 4.7 MMboe. This was an 9.6% decrease compared with H1 2024 due to natural field decline and planned maintenance downtime.
In H1 2025, reliability at Shenzi was 98.8%. Woodside is operator and holds a 72% participating interest.
Atlantis
The Atlantis conventional offshore oil and gas development includes a semi-submersible facility and is one of the largest producing fields in
Woodside’s share of production in H1 2025 was 6.0 MMboe. This was a 17.6% increase compared with H1 2024 due to no turnaround activities, uplift from planned interventions, and new production from an infill sidetrack well.
In H1 2025, a FID was taken for the
Woodside holds a 44% non-operating participating interest.
Mad Dog
Mad Dog is an offshore conventional oil and gas field located in
Woodside’s share of production in H1 2025 was 5.3 MMboe. This was a 11.7% decrease compared with H1 2024 due to natural field decline.
Infill drilling and completion activities were ongoing throughout H1 2025 in support of both the Argos and A-Spar facilities. The Mad Dog Southwest Extension was brought online subsequent to the period, with first oil achieved 25 months after finishing the appraisal well. Woodside holds a 23.9% non-operating participating interest.
Woodside was operator and held a 45.0% participating interest in the
Subsequent to the period, Woodside completed the divestment of its
Marketing and Trading |
The marketing segment’s EBIT in H1 2025 was
In H1 2025, Woodside signed three long-term LNG sales and purchase agreements (SPAs). This included two long-term SPAs with Uniper for the supply of 1.0 Mtpa from
Woodside signed non-binding heads of agreements with
The execution of these agreements highlights sustained global demand for Woodside’s LNG and reinforces the strategic advantage of our diversified portfolio in driving long-term growth and value.
Oil sales increased in H1 2025 from H1 2024, reflecting a full six months of production from the Sangomar field in
A record quantity of trucked LNG, approximately 1,233 TJ and equivalent to 1,200 trailers, was delivered in H1 2025 to customers in northern
On the east coast of
Woodside continued its marketing activities to support the offtake of lower-carbon ammonia from the
Woodside SPAs with Commonwealth LNG, executed in
Projects |
The
The field is being developed through new offshore facilities connected by a 433 km pipeline to a second LNG train at the existing
The expansion of the
The Project was 86% complete at the end of H1 2025, excluding Pluto Train 1 modifications. First LNG cargo is targeted for the second half of 2026.
The FPU achieved significant milestones throughout the first half of 2025. The construction of both the hull and topsides was completed, and the structures were successfully loaded out and connected during the floatover activities in
Subsequent to the period, subsea installation, testing and pre-commissioning was completed, ready for the FPU arrival and final subsea hook up.
Batch drilling of the eight initial development wells continued, and subsequent to the period the third development well was drilled and completed, and the fourth well was drilled. Reservoir properties were in line with expectations, and the anticipated deliverability of the wells remains on track.
Construction activities at the Pluto Train 2 site continued with piping, cable installation and electrical commissioning progressing, with the workforce reaching peak numbers.
Civil, structural and piping works at the Pluto Train 1 modifications site are ongoing with the largest concrete pour for the modifications project completed. Construction activity at the module yard ramped up throughout the half.
Subsequent to the period, the
Woodside is operator and holds a 74.9% participating interest in
Trion
Trion is an offshore oil development located in
The Project was 35% complete at the end of H1 2025. First oil is targeted for 2028.
The FPU achieved key milestones during H1 2025 including finalising the detailed design, moving hull blocks into the dry dock, progressing construction of three topside modules and the living quarters, and completing the fabrication of FPU turbo machinery and equipment.
The FSO facility detailed engineering progressed, with fabrication scheduled to commence in H2 2025. Fabrication of the disconnectable turret mooring continued and fabrication of the FSO and FPU anchor piles commenced.
The design, procurement and manufacturing of subsea and gathering line equipment are progressing, with all subsea equipment, trees, and topside control systems ordered and fabrication underway.
All major contract awards have been completed, including drilling and completion services, gas pipeline installation, FSO operating and maintenance contracts, and support vessels.
In
Woodside is the operator and holds a 60% participating interest in the Project.
Beaumont New Ammonia
Beaumont New Ammonia is an under-construction lower-carbon ammonia project in
Construction on Train 1 continues to be managed by OCI and the Project is 95% complete at the end of H1 2025. Project completion and associated payment of the remaining 20% of the acquisition consideration is expected in 2026.
In H1 2025, progress included completion of storage tank construction and compressor alignment. The electrical substation was also completed with the primary transformer ready to switch from temporary to permanent power in H2 2025. Pre-commissioning activities commenced as Project construction nears completion.
Woodside is progressing marketing activities in support of ammonia sales from Train 1.
Woodside holds a 100% participating interest and upon handover of the Project from OCI will become operator.
Louisiana LNG
Louisiana LNG is a fully permitted LNG development located near
Woodside approved an FID to develop the initial three-train, 16.5
In
Louisiana LNG continues to receive strong interest from high-quality potential partners and will progress sell-down discussions while retaining a controlling ownership interest.
Following FID, a full notice to proceed was issued to Bechtel for construction. All high-value orders and major purchase orders for equipment and bulk materials have been released and committed. Train 1 was 22% complete at the end of H1 2025, with activities focused on progressing the marine offloading facility, marine dry excavation, and civil works.
Woodside is building the Line 200 lateral pipeline, which will supply a significant portion of the pipeline transportation capacity requirement. Orders have been placed for long lead items for the pipeline. Woodside will continue to secure additional pipeline transportation capacity on third-party pipelines, with a continued focus on ensuring diverse and reliable feedgas sources for Louisiana LNG.
The
Woodside also submitted an application to the
Woodside is the operator and holds a 100% participating interest in
Hydrogen Refueller @H2Perth
The Hydrogen Refueller @H2Perth is a self-contained hydrogen production, storage and refuelling station located in
Construction activities commenced for the Project with major equipment packages including electrolysers and compressors installed on site. Major civil works are near complete and both electrical cable and tubing installation have commenced.
Woodside is targeting ready for startup in Q4 2025, with first hydrogen production expected in the first half of 2026.
Decommissioning |
Woodside continued execution of planned decommissioning activities in H1 2025, spending approximately
Woodside has progressed planned decommissioning activities across the
In H1 2025, Woodside concluded the ten-well Stybarrow plugging campaign and successfully completed the plug and abandonment of the three remaining wells at the Minerva field.
In February, final infrastructure was recovered from
Woodside experienced a Tier 1 process safety event when unexpected fluids were released during flushing activities of a Griffin subsea flowline. Water quality monitoring identified no impact on the environment.
Woodside is evaluating decommissioning work plans for Minerva, Stybarrow and Griffin. The as-left condition on some closed sites has continued to present challenges for safe and efficient execution of decommissioning and learnings are being applied to improve planning and execution. These challenges are the primary driver of a
At
Detailed engineering and execution planning, including submission of primary and secondary environmental approvals to regulators for assessment, is well advanced for the
Exploration and Development |
Browse
The Browse development comprises the Calliance, Brecknock and Torosa gas and condensate fields located approximately 425 km north of Broome,
Work continued on the Browse to
In
In
Woodside is operator and holds a 30.6% participating interest.
Sunrise
The Sunrise development comprises the Sunrise and Troubadour gas and condensate fields, located approximately 450 km north-west of Darwin and 150 km south of Timor-Leste.
Woodside continues to work with the Timor-Leste and Australian Governments and the Sunrise Joint Venture participants to assess and address technical and commercial considerations to help enable the desired commercialisation of the fields.
Woodside conducted a visit to Timor-Leste's south coast as a potential location for processing Sunrise gas. The visit included a review of the Timor-Leste Government’s proposed site at Natarbora for a range of facilities, including an LNG plant, and a proposed site at Suai for a supply base.
Woodside is operator and holds a 33.44% participating interest.
Calypso
Calypso is located approximately 220 km off the coast of
The
Woodside is operator and holds a 70% participating interest.
Liard
The Liard field is an unconventional gas field located in
Woodside is working with the asset operator to develop a strategy for full field development, as well as with its partners in Rockies LNG to potentially export LNG through the proposed
Woodside holds a 50% non-operating participating interest in Liard.
Exploration
Woodside’s exploration activities continue to prioritise disciplined portfolio optimisation, including exiting blocks that are no longer considered prospective, such as Blocks 1, 3, and 4 in the
In
In the US, Woodside continues to actively manage its acreage position offshore
New energy |
NeoSmelt
In H1 2025, Woodside formally joined the
Woodside is non-operator and holds a 20% participating interest.
H2Perth
H2Perth is a proposed commercial-scale liquid hydrogen facility to be located in
In H1 2025, Woodside commenced pre-FEED studies for the initial phase of the Project.
Woodside is operator and holds a 100% participating interest.
H2OK
Woodside has made the decision to exit the proposed
H2TAS
In H1 2025, Woodside formalised its exit from H2TAS.
Business developments |
In May, Woodside entered into a non-binding collaboration agreement with
Woodside signed a non-binding memorandum of understanding with
|
Woodside is progressing CCS opportunities in
In H1 2025, the proposed
The Bonaparte CCS Assessment Joint Venture commenced pre-FEED and was awarded Major Project Status by the Australian Government.
Woodside continues to assess the South East Australia CCS opportunity.
Woodside continues to acquire carbon credits through both market purchases and the development of its own carbon origination projects.36
During H1 2025, environmental planting activities under Woodside’s
Woodside-funded international carbon origination projects in
Climate and Sustainability |
Health, personal and process safety
In H1 2025, the year-to-date lost time frequency rate was 0.26 compared with 0.47 for full-year 2024, and the total recordable injury rate was 2.02 compared to 2.44 recorded for full-year 2024. There were no fatalities or permanent injuries recorded in H1 2025.
In H1 2025, Woodside experienced a Tier 1 process safety event when unexpected fluids were released during flushing activities of a Griffin subsea flowline. Water quality monitoring identified no impact to the environment.
Woodside is focussed on embedding simplified safety processes, implementing improvements in the engineering systems to manage hardware, and promoting a learning culture through the Field Leadership Program.
Climate
Woodside is on track to meet its corporate 2025 net equity Scope 1 and 2 greenhouse gas emissions reduction target.37 During the half, achievements included the high reliability of the Sangomar gas injection system which lead to reduced flaring emissions and improvements at KGP that reduced the assist gas for the operational flares and improved the efficiency of the domestic gas compressor operating envelope.
Woodside submitted its
First Nations cultural heritage and engagement
During H1 2025, Woodside continued to engage with multiple Traditional Owner representative bodies in
Woodside completed a planned annual cultural heritage audit of
Subsequent to the period, Woodside welcomed the inscription of the Murujuga Cultural Landscape on the World Heritage List by
Environment and biodiversity
In H1 2025, there were no significant environmental impacts from our operations. Woodside continued to implement a robust and systematic approach to environmental management of our activities.
To support biodiversity positive outcomes in the regions and areas in which we undertake activities, Woodside is working closely with local partners to identify and deliver measurable positive biodiversity outcomes across a range of locations in
In H1 2025, Woodside finalised Biodiversity Management Plans for Trion, Beaumont New Ammonia and Louisiana LNG.
Local content
In H1 2025, the Pluto Train 1
Woodside also extended its agreement with
In
A contracting plan has been put in place to support operations planning for Trion. The plan includes strategies for compliance with local content requirements, including a framework to support local companies through specialised supplier development programs, networking, and integration. A key element of the strategy for local content is collaboration with Project participants to leverage potential suppliers and share synergies.
Social contribution
Woodside published its 2024 Social Investment Impact Report in
Directors’ Report |
The directors of
Board of directors
The names of directors in office during or since the end of the 2025 half-year are as follows:
Mr |
Ms Meg O’Neill (CEO and Managing Director) |
Mr |
Mr |
Mr |
Ms |
Mr |
Ms |
Mr Tony O’Neill |
Ms |
Mr Ben Wyatt |
|
Rounding of amounts
Auditor’s Independence Declaration
The Auditor’s Independence Declaration, as required under section 307C of the Corporations Act 2001, is set out on page 18 and forms part of this report.
Signed in accordance with a resolution of the directors.
R J Goyder, AO
Chair
____________________ |
1 These are alternative performance measures which are non-IFRS measures that are unaudited. Refer to Alternative Performance Measures on pages 55 – 57 and Non-IFRS Measures on page 63 for more information. |
2 Target is for net equity Scope 1 and 2 greenhouse gas emissions reduction relative to a starting base of 6.32 Mt CO2-e which is representative of the gross annual average equity Scope 1 and 2 greenhouse gas emissions over 2016-2020 and which may be adjusted (up or down) for potential equity changes in producing or sanctioned assets with a FID prior to 2021. Net equity emissions include the utilisation of carbon credits as offsets. |
3 Cash flow from operating activities less cash flow from investing activities, adjusted for the capital contribution from Stonepeak for the development of Louisiana LNG. |
4 Includes production of 98.6 MMboe from Woodside reserves and 0.6 MMboe primarily from feed gas purchased from Pluto non-operating participants processed through the Pluto-KGP Interconnector. |
5 Gas hub indices include Japan Korea Marker (JKM), TTF and |
6 Capital additions on Louisiana LNG adjusted for the cash contribution from Stonepeak. |
7 Calculated based on Woodside’s closing share price on |
8 This is an alternative performance measure which is a non-IFRS measure that is unaudited. Refer to Alternative Performance Measures on pages 55 – 57 for a reconciliation for these measures to Woodside’s financial statements and Non-IFRS Measures on page 63 for more information. |
9 Net profit after tax attributable to equity holders of the parent. |
10 The global operations effective income tax rate (EITR) of 21.0% (2024: 6.9%) is calculated as the Group’s income tax expense divided by profit before income tax. The underlying EITR is 30.9% when excluding the recognition of a |
11 Capital additions on property, plant and equipment and evaluation capitalised. Excludes exploration capitalised and adjusted for the capital contribution received from Stonepeak for the development of Louisiana LNG. |
12 Exploration and evaluation expenditure less amortisation costs and prior year exploration expense written off. |
13 Cash flow from operating activities less cash flow from investing activities, adjusted for the capital contribution from Stonepeak for the development of Louisiana LNG. |
14 Includes production of 98.6 MMboe from Woodside reserves and 0.6 MMboe primarily from feed gas purchased from Pluto non-operating participants processed through the Pluto-KGP Interconnector. |
15 The conversion factors used throughout this report are set out on page 60, unless otherwise stated. Sales volumes differ from production volumes primarily due to the timing of liftings and the exclusion of third-party purchased volumes. |
16 Sales volumes exclude periodic adjustments reflecting the arrangements governing Wheatstone LNG sales. The 2024 comparative sales volumes and sales volumes per day have been restated by 0.1 MMboe and 3 MMscf/d respectively to exclude the periodic adjustments. |
17 Comparisons are to half-year ended |
18 Calculated based on Woodside’s closing share price on |
19 These are alternative performance measures which are non-IFRS measures that are unaudited. Refer to Alternative Performance Measures on pages 55 – 57 and Non-IFRS Measures on page 63 for more information. |
20 Cash flow from operating activities less cash flow from investing activities, adjusted for the capital contribution from Stonepeak for the development of Louisiana LNG. |
21 Completion of the transaction is subject to conditions precedent. See “Woodside simplifies portfolio and unlocks long-term value” announced |
22 Completion of the transaction is subject to conditions precedent. See “Woodside simplifies portfolio and unlocks long-term value” announced |
23 Refer to Woodside’s Reserves Statement dated |
24 See the announcement “Woodside strengthens its Australian operations” released |
25 Refer to Notes to petroleum reserves and resources on page 64 for details of disclaimers. |
26 Under the terms of the sale agreement between Capricorn and Woodside, Capricorn is responsible for ~50% of the total amount. |
27 Includes a base purchase price of |
28 Production of lower-carbon ammonia is conditional on the supply of carbon abated hydrogen and ExxonMobil’s CCS facility becoming operational. |
29 Lower-carbon ammonia is characterised here by the use of hydrogen with emissions abated by carbon, capture, and storage (CCS), with an expected ammonia lifecycle (Scope 1, 2 and 3) carbon emissions intensity of 0.8 tCO2/tNH3 (based on contracted intensity threshold with Linde) relative to unabated ammonia with a lifecycle (Scope 1, 2 and 3) carbon emissions intensity of 2.3 tCO2/tNH3 ( |
30 The Project has received funding from the Hydrogen Fuelled Transport Project Funding Process as part of the Western Australian Government’s Renewable Hydrogen Strategy. |
31 Woodside uses the term lower-carbon to describe the characteristic of having lower levels of associated potential GHG emissions when compared to historical and/or current conventions or analogues, for example relating to an otherwise similar resource, process, production facility, product or service, or activity. When applied to Woodside's strategy, please see the definition of lower-carbon portfolio in the Glossary on pages 58-60. |
32 Energy supply may include hydrogen, natural gas and/or electricity. |
33 The views expressed herein are not necessarily the views of the Australian Government, and the Australian Government does not accept responsibility for any information or advice contained herein. |
34 Lower-carbon ammonia is characterised here by the use of hydrogen with emissions abated by carbon, capture, and storage (CCS), with an expected ammonia lifecycle (Scope 1, 2 and 3) carbon emissions intensity of 0.8 tCO2/tNH3 (based on contracted intensity threshold with Linde) relative to unabated ammonia with a lifecycle (Scope 1, 2 and 3) carbon emissions intensity of 2.3 tCO2/tNH3 ( |
35 Completion of the transaction is subject to conditions precedent. See “Woodside simplifies portfolio and unlocks long-term value” announced |
36 Origination refers to carbon offset projects developed by Woodside or third-party project developers, characterised by (i) the provision by Woodside of up-front investment or funding; (ii) Woodside either being a majority participant in the project or a recipient of carbon credits from the project (or both); and (iii) the acceptance of risk by Woodside in relation to carbon credit delivery. |
37 Target is for net equity Scope 1 and 2 greenhouse gas emissions reduction relative to a starting base of 6.32 Mt CO2-e which is representative of the gross annual average equity Scope 1 and 2 greenhouse gas emissions over 2016-2020 and which may be adjusted (up or down) for potential equity changes in producing or sanctioned assets with a FID prior to 2021. Net equity emissions include the utilisation of carbon credits as offsets. This means net equity Scope 1 and 2 greenhouse gas emissions for the 12-month period ending |
38 Woodside defines biodiversity positive as a project or investment that has measurable benefits to 1) threatened or keystone species; or 2) restores or regenerates natural habitat; or 3) removes threatening processes or enhances ecological function. A keystone species is a species that has a disproportionately large effect on its natural environment relative to its abundance. |
View source version on businesswire.com: https://www.businesswire.com/news/home/20250818539549/en/
M: +61 484 112 469
E: christine.abbott@woodside.com
Source: