Blue Moon Announces Results of Nussir Project Feasibility Study
Strong Economic Results, Including Average Annual Free Cash Flow of
The Company believes the results of the Feasibility Study confirm the Project's potential as a robust, long-life asset with strong economics, including base case average annual free cash flow of
Highlights:
- Total measured and indicated resource for Project is 28.72 Mt at 1.20% CuEq grade (see notes in Table 2).
- Total proven and probable reserve estimate is 24.98 Mt at 0.99% CuEq grade (see notes Table 3).
- Life of mine is 13 years with nominal mill throughput of 6,000 tonnes per day.
- Life of Mine (LOM) average annual production of 19 kt of CuEq including an average of 3,600 ounces of gold and 546,000 ounces of silver in the consensus price scenario.
- LOM total cash costs (net of by-products) of
$0.95 per pound of copper and all-in sustaining costs of$2.05 per pound of copper resulting in an all-in sustaining cost cashflow margin of 43% utilizing consensus pricing. - After-tax Net Present Value of
$235 million (8% discount rate) at a long-term copper price of$4.78 per pound, gold price of$3,515 per ounce and silver price of$45.26 per ounce. At consensus pricing the payable metal mix breakdown is 77% copper, 6% gold and 13% silver. - After-tax Internal Rate of Return of 19% for the 13 year mine life and consensus pricing and 31% at spot pricing.
- Initial capital expenditures of
$184 million .
Additionally, the Company has advanced the basic engineering for the Project and has placed purchase orders for the long lead equipment required for the process plant (SAG mill,
The FS was completed by
|
Table 1: Project Economics and Key Parameters |
|||
|
Commodity Pricing |
Units |
Consensus (1) |
Spot (2) |
|
Milling Capacity |
tpd |
6,000 |
6,000 |
|
|
Years |
13 |
13 |
|
LOM Cu Production |
kt |
185 |
185 |
|
LOM CuEq Production |
kt |
241 |
261 |
|
LOM Average Cu Production(3) |
ktpa |
14.6 |
14.6 |
|
LOM Average CuEq Production(3) |
ktpa |
19.0 |
19.6 |
|
Average annual free cash flow(3) |
US$m |
|
|
|
Initial Capital Costs |
US$m |
|
|
|
Sustaining Capital Costs |
US$m |
|
|
|
LOM C1 Cash Cost (net of by-products) |
US$/lb |
|
|
|
|
US$/lb |
|
|
|
Post-tax NPV (0%) |
US$m |
|
|
|
Post-tax NPV (8%) |
US$m |
|
|
|
IRR |
% |
19.0 |
31.2 |
|
(1) Consensus pricing assumes: 2028 |
|
(2) Spot prices are based on |
|
(3) The average values are based on average of the years with full production |
MINERAL RESOURCES ESTIMATE ("MRE")
|
Table 2: Mineral Resource Statement
|
|||||
|
Classification |
Tonnes (millions) |
Cu Grade (%) |
Au |
(g/t) |
Cu Eq Grade (%) |
|
Measured |
2.69 |
1.08 |
0.18 |
12.8 |
1.31 |
|
Indicated |
26.03 |
1.01 |
0.11 |
12.3 |
1.19 |
|
Measured & Indicated |
28.72 |
1.02 |
0.12 |
12.3 |
1.20 |
|
Inferred |
31.99 |
1.01 |
0.14 |
14.6 |
1.23 |
Notes:
|
1. |
CIM 2014 Definitions Standards were followed for classification of Mineral Resources. |
|
2. |
A minimum mining width of 2.0 m was applied in making the resource estimate constraint wireframes. These wireframes were generated using a preliminary MSO. |
|
3. |
Density values for Nussir were estimated from density sample values or assigned default average values where insufficient samples occur nearby. |
|
4. |
MRE constraint wireframes were generated for a cut-off grade of 0.30% Cu, related to potential underground mining. |
|
5. |
Metal prices assumed for this MRE were |
|
6. |
CuEq Grade=Cu Grade+0.00781*Ag_Grade+0.740* |
|
7. |
Metallurgy recovery assumptions were 96% Cu, 80% Ag and 93% Au, which stem from SGS metallurgical test work completed in 2022. |
|
8. |
The cut-off grade of 0.30% Cu was derived from the price and recovery values above, as well as a smelter payability of 97.3% and an assumed total operating cost |
|
9. |
Rounding may result in apparent summation differences between tonnes, grades and metal content; not considered material. |
|
10. |
Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. CIM Definition Standards were followed for classification of Mineral Resources. |
|
11. |
Mineral Resources shown are inclusive of Mineral Reserves. |
|
12. |
Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. |
MINERAL RESERVES ESTIMATE
The tonnage, grades, and classification of the Total Mineral Reserves captured within the FS Mine Plan are summarized below.
|
Table 3: Mineral Reserves |
|||||
|
Classification |
Tonnes |
Cu Grade (%) |
(g/t) |
(g/t) |
Cu Eq Grade |
|
Proven |
2.64 |
0.80 |
0.13 |
10.15 |
1.01 |
|
Probable |
22.34 |
0.81 |
0.09 |
10.36 |
0.99 |
|
Proven & Probable |
24.98 |
0.81 |
0.09 |
10.34 |
0.99 |
Notes:
|
1. |
Above Reserves estimate follows CIM (2019) MRMR Best Practice Guidelines including CIM Definition Standards for classification. |
|
2. |
Mining methodology is long hole open stope with minimum mining width of 3 m and mining recovery of 95% applied. |
|
3. |
Dilution applied to stopes using ELOS method correlated with geotechnical conditions. |
|
4. |
Reserves are based on copper price of |
|
5. |
In-Situ NSR Cut off is |
|
6. |
Copper recovery is 96%, gold is 84% and silver is 95%. |
|
7. |
Concentrate treatment cost is |
|
8. |
Refining costs are |
|
9. |
Freight is |
|
10. |
Numbers presented in this table may not add up to the totals provided due to rounding. |
MINING AND PROCESSING
The mining method used for the FS is Long Hole Open Stoping (LHOS) method with ribs and sill pillars to consistently sustain the production and mill throughput design rate. Required infrastructure to support the mine operation have been included in the design, including materials handling equipment. Trucking and mobile equipment have been optimized in the mine design along with implementation of conveyors for both crushed ore and waste.
Underground mobile crushers are utilized followed by a grinding circuit including a semi-autogenous grinding (SAG) mill and a ball mill located on surface prior to flotation. The flotation concentrate is filtered using a plate and frame pressure filter and stored in a storage warehouse prior to shipping through the existing and operational port and ship loaders. The mine and process facility will be powered by an existing 132 kV power line. Fresh water requirements for the process plant and the mine will be provided from an existing water dam using an existing buried pipeline. A water treatment plant has been included to treat the underground mine water to a quality suitable for reuse within the processing plant, thereby reducing demand for freshwater abstraction from the water reservoir and to treat the excess mine water to a quality suitable for controlled discharge during upset conditions (e.g. processing plant shutdowns or maintenance), in accordance with applicable Norwegian and EU environmental standards.
ENVIRONMENTAL AND PERMITTING
The primary permits required for mining projects in
PROJECT TIMELINE
A project execution plan and target schedule have been developed as part of the Feasibility Study to outline the durations and key activities for achieving commercial production at the Project. The Project schedule defined the construction completion of
|
Table 4: Project Timeline |
|
|
Milestone |
Target Date |
|
EPC Contract Award |
|
|
|
|
|
Mechanical Completion |
|
|
Start of No-Load Commissioning |
|
|
Start of System Handover to Operation |
|
|
Start of Production and Ramp-up |
|
|
Final Certification |
|
ECONOMIC IMPACT
The Company expects the Project to generate significant economic benefits at both the local and national levels. At peak construction, the Company expects to employ, directly or indirectly, approximately 200 personnel, and approximately 100 personnel during commercial production operations, with indirect employment estimated at two to three times these levels through supporting industries and services.
The Company is implementing strategies to maximize the number of long-term employees residing locally, which is expected to provide a sustained boost to the regional economy and support the creation of additional long-term indirect employment associated with population growth.
Based on the assumptions used in the Feasibility Study and applying current Norwegian fiscal regimes, the Project is expected to generate substantial government revenues over its life. Using long-term consensus commodity prices, life-of-mine Norwegian government royalties are estimated at approximately
At spot commodity prices, life-of-mine Norwegian government royalties are estimated at approximately
Opportunity Case
The FS reserve estimate excludes inferred material from the resource estimate. The potential conversion of this inferred material supports the opportunity case and showcases the potential of the life of mine extension to 17 years, considering the same production throughput.
|
Table 5: Opportunity Case (1) Economics and Key Parameters |
|||
|
Commodity Pricing |
Units |
Consensus (2) |
Spot (3) |
|
Milling Capacity |
tpd |
6,000 |
6,000 |
|
|
Years |
17 |
17 |
|
LOM Cu Production |
kt |
294 |
294 |
|
LOM CuEq Production |
kt |
386 |
420 |
|
LOM Average Cu Production(4) |
ktpa |
16.0 |
16.0 |
|
LOM Average CuEq Production(4) |
ktpa |
20.9 |
22.8 |
|
Average annual free cash flow(4) |
US$m |
|
|
|
Initial Capital Costs |
US$m |
|
|
|
Sustaining Capital Costs |
US$m |
|
|
|
LOM C1 Cash Cost (net of by-products) |
US$/lb |
|
|
|
|
US$/lb |
|
|
|
Post-tax NPV (0%) |
US$m |
|
|
|
Post-tax NPV (8%) |
US$m |
|
|
|
IRR |
% |
19.6 |
31.1 |
|
(1) Opportunity case includes additional inferred resources (using 50% conversion rate) that are considered too speculative geologically to have been categorized as reserves. |
|
(2) Consensus pricing assumes: 2028 |
|
(3) Spot prices are based on |
|
(4) The average values are based on average of the years with full production |
QUALIFIED PERSONS
The FS was prepared by both
-
Chris Hughes-Narborough (Worley QP),Institute of Materials , Minerals and Mining (IMMM) – Chapters 13 and 17 -
Martin Prior (Worley QP), Fellow (FSAIMM), ECSA – Chapters 1-5, 18, 19, 21,22, 24, 25, 26, and 27 -
Roy R. Levesque (Worley QP),P.Eng . – Chapters 15 and 16 -
Lumin Ma (Worley QP), Ph.D,P.Eng – Sections 1.8, 16.3, 26.4, and Chapter 27 -
Adam Wheeler (independent contractor), Mining Consultant,C. Eng ,Eur Ing , FIMMM, Exploration, geological setting, deposit – Chapters 6-12, 14, and 23 -
Susan Abell (Worley QP), Professional Scientist registered with theSouth African Council for Natural Scientific Professions – Chapter 20
The technical and scientific information of this news release has also been reviewed and approved by Mr.
About Blue Moon
Blue Moon is advancing 5 brownfield polymetallic projects, including the Nussir copper-gold-silver project in
Neither
CAUTIONARY STATEMENT REGARDING ESTIMATES OF MINERAL RESOURCES
This news release uses the terms measured, indicated and inferred Mineral Resources as a relative measure of the level of confidence in the Mineral Resource estimate. Readers are cautioned that Mineral Resources are not Mineral Reserves and that the economic viability of resources that are not Mineral Reserves has not been demonstrated. The Mineral Resource estimate referenced in the Technical Report and summarized in this news release may be materially affected by geology, environmental, permitting, legal, title, socio-political, marketing or other relevant issues. Mineral Resources in the Technical Report are reported using the 2014 CIM Definition Standards and were estimated in accordance with the CIM 2019 Best Practices Guidelines, as required by NI 43-101. Under NI 43-101, estimates of inferred Mineral Resources may not form the basis of feasibility or pre-feasibility studies or economic studies except for preliminary economic assessments. Readers are cautioned not to assume that further work on the stated Mineral Resources will lead to Mineral Reserves that can be mined economically.
CAUTIONARY STATEMENT REGARDING FORWARD LOOKING STATEMENTS
This news release contains "forward-looking information" under applicable Canadian securities legislation. Except for statements of historical fact relating to the Company, information contained herein constitutes forward-looking information, including, but not limited to, any information as to the Company's strategy, objectives, plans or future financial or operating performance. Forward-looking statements are characterized by words such as "plan", "expect", "budget", "target", "project", "intend", "believe", "anticipate", "estimate" and other similar words or negative versions thereof, or statements that certain events or conditions "may", "will", "should", "would" or "could" occur. In particular, forward-looking information included in this news release includes, without limitation, statements with respect to the Company's expectations in connection with the production, development and expansion plans at the Project being met; the Company's expectations relating to the performance of the Project; the estimation of Mineral Reserves and Mineral Resources; the timing and amount of estimated future production; the estimation of the LOM of the Project; the timing and amount of estimated future capital and operating costs; the costs and timing of development activities (including the estimated timing of achieving the development milestones set out above); the effect of government regulations (or changes thereto) with respect to restrictions on production, export controls, income taxes, royalties, equity interests, expropriation of property, repatriation of profits, environmental legislation, land use, water use, land claims of local people, mine safety and receipt of necessary permits; the Company's community relations in the locations where it operates and the further development of the Company's social responsibility programs; and the Company's outlook and guidance.
Information contained in forward-looking statements is based upon certain material assumptions that were applied in drawing a conclusion or making a forecast or projection, including the assumptions, qualifications and limitations relating to the Feasibility Study (including, but not limited to, the Mineral Resources, Mineral Reserves, production profile, mine design and project economics); the ability and timing of the Company to publish and file the Technical Report; the Company being construction and operation ready and the timing for the commencement of construction activities; the ability and timing of the Company to reach a formal positive final investment decision in respect of the Project; the ability and timing of the Company to secure a project financing package to fund construction activities at the Project and the terms of such financing; the impact and potential of the Project on shareholders, the surrounding community and other stakeholders; the ability to successfully engage and collaborate with stakeholders; the ability to engage with and manage the activity of those groups opposed to the development the Project; sustainability and environmental impacts of operations at the Project; Mineral Resource category conversion; the timing and status of any additional required permits or amendments thereto, or other regulatory approval requirements; the future development and operations at the Project; the capital resources available to the Company; the ability of the Company to execute its planned activities, including as a result of its ability to seek additional funding; management's perceptions of historical trends, current conditions and expected future developments; the ability and timing for the Project to reach commercial production (if at all); the expected cash flow (and underlying assumptions) in respect of the Project; the results (if any) of further exploration work to define and expand Mineral Resources; the ability of exploration work (including drilling) to accurately predict mineralization; the ability of the Company to expand Mineral Resources beyond current Mineral Resource estimates and to convert some or all of these Mineral Resources to higher categories of Mineral Resources or to Mineral Reserves; the ability for the Company to expand throughput or increase production at the Project; the ability of the Company to discover additional deposits within the Project area; the ability of the Company to complete its development objectives for the Project in the timing contemplated and within expected costs (if at all); the ability to adapt to changes in gold, silver, copper and other commodity prices, estimates of costs, including the cost and availability of energy resources required to develop and operate the Project given the disruptions to regular traffic flow through the
The Company considers its assumptions to be reasonable based on information currently available, but cautions the reader that their assumptions regarding future events, many of which are beyond the control of the Company, may ultimately prove to be incorrect since they are subject to risks and uncertainties that affect the Company and its business. Such risks and uncertainties include, among others, risks relating to third-party approvals, including the issuance of permits by the government, capital market conditions and the Company's ability to access capital on terms acceptable to the Company for the contemplated development of the Project; counterparty, credit, liquidity and risks related to the Company's ability to service its debt obligations; regulatory framework and presence of laws and regulations that may impose restrictions on mining; the ability of exploration activities (including drill results and chip sampling, and face sampling results) to accurately predict mineralization; errors in management's geological modelling; the timing and ability of the Company to obtain and maintain required approvals and permits; risks relating to the development, construction and start-up of new mines and mining activities, including but not limited to health, safety and environmental risks and hazards to which the Company's operations are subject, adverse environmental and climatic conditions, unusual and unexpected geologic conditions, equipment failures, the availability and performance of contractors and suppliers, and cost overruns; the global economic climate (including with respect to the cost and availability of energy resources required to develop and operate the Project given the disruptions to regular traffic flow through the
View original content to download multimedia:https://www.prnewswire.com/news-releases/blue-moon-announces-results-of-nussir-project-feasibility-study-302743955.html