LODE GOLD'S NEW MINERAL RESOURCE ESTIMATE: 1.11 MOZ OF GOLD - 18.8 MT AT 1.84 G/T AU (MEASURED & INDICATED) AND 1.99 MOZ OF GOLD (INFERRED) - 33.1 MT AT 1.86 G/T AU AT FREMONT GOLD MINE
Significant Growth in Resource Confidence
Using stricter parameters for Reasonable Prospects for Eventual Expectations of Extractions ("RPEEE") including underground mine design,
In the previous 2025 MRE when the price of gold was USD
At a 1 g/t Au cut-off, the updated MRE defines:
- 1.11 million oz of gold (
Moz Au ) - 18.7 Mt at a grade of 1.84 g/t Au (Indicated) - 1.98 million oz of gold (
Moz Au ) - 33.1 Mt at a grade of 1.86 g/t Au (Inferred)
This MRE (Reference: Figure 1) is based only on three of the seven deposits:
Jonathan Hill, Chair of Lode Gold's Technical Committee and Director of the Board commented: "The integration of those new 7,000 historical samples, including underground channel samples collected in 1986 with external laboratory certification, has been a key factor in improving the overall quality and confidence of the Mineral Resource Estimate. These data have allowed us to validate continuity of mineralization, significantly strengthening both the geological model and the classification of gold resources.The reclassification to M&I category is one of the key steps in derisking the project as we advance towards PFS, evaluating various optimized underground mining methods."
Enhanced Geological Model and Data Integration
The updated resource is supported by the integration of more than 7,000 new underground channel samples and drill holes (for a total of over 38,000 samples), which have significantly strengthened the geological and block models. These additional data points have confirmed the continuity of mineralization in areas that were previously based largely on extrapolation, improving both the confidence and the spatial definition of the mineralized system.
Updated Mineral Resource Estimate
|
Category |
Cut-off Grade (g/t Au) |
Tonnes (t) |
Grade (Au g/t) |
Gold (oz) |
|
Indicated |
1 |
18,776 |
1.84 |
1,110,444 |
|
|
|
|
|
|
|
Inferred |
1 |
33,107 |
1.86 |
1,978,568 |
- Reported figures have been rounded in accordance with the level of accuracy appropriate for a Mineral Resource Estimate; therefore, minor discrepancies may occur in totals due to rounding adjustments.
- The Mineral Resource Estimate has been prepared in compliance with National Instrument 43-101 ("NI 43-101") requirements, as well as the CIM (2019) Best Practice Guidelines for Mineral Resource and Mineral Reserve Estimation and the CIM (2014) Definition Standards.
- Mineral Resources do not constitute Mineral Reserves and therefore have not demonstrated economic viability. Inferred Mineral Resources are considered too speculative geologically to have economic considerations applied that would enable them to be categorized as Mineral Reserves. Although there is no certainty that further exploration will result in upgrading Inferred Resources to higher-confidence categories, continued drilling and technical work could reasonably support conversion of a significant portion to M&I Resources.
- To the best of the Company's knowledge, there are no known environmental, permitting, legal, title, fiscal, socio-economic, political, or marketing issues that would materially impact the current Mineral Resource Estimate.
In preparing the updated Mineral Resource Estimate, the Company applied the concept of RPEEE as required under NI 43-101 and CIM Definition Standards with considerations and assumptions including:
- Incorporating the current MRE with preliminary mineability considerations, unlike historical resource models focused primarily on grade distribution.
- Demonstrating reported material has realistic potential for economic extraction using plausible underground mining methods.
- Supporting independent mining engineering work completed using a conceptual bulk underground bulk mining scenario.
- Generating mineable stope optimization within the mineralized envelope with cut-off grade of 0.82 g/t Au applied (Reference: Figure 2) and deriving from preliminary operating cost assumptions from the Company's local
California mining contractor with a gold price forecast of US$3,500 /oz. - Including only mineralization considered potentially mineable within conceptual stopes in the reported resource.
- Diluting resource within these mining stopes to better reflect the grades that could realistically be encountered during extraction, rather than relying solely on undiluted in-situ block grades.
|
Diluted grade in the RPEEE Stopes at 1 g/t cut-off |
|
Undiluted grade at 1 g/t cut-off |
||||||
|
Category |
Tons |
Au g/t |
Au (oz) |
|
Category |
Tons |
Au g/t |
Au (oz) |
|
Indicated |
18,776,346 |
1.84 |
1,110,444 |
|
Indicated |
14,818,615 |
2.40 |
1,143,384 |
|
Inferred |
33,106,965 |
1.86 |
1,978,568 |
|
Inferred |
30,638,858 |
2.12 |
2,090,454 |
As a result of applying these RPEEE constraints and mining dilution factors, the average reported gold grades are lower than those generated in earlier purely geological models. However, the Company believes the updated estimate provides a more realistic representation of the deposit's potential economic extraction characteristics and establishes a stronger technical foundation for future engineering studies, including mine planning, reserve conversion and the advancement toward a Preliminary Feasibility Study.
The scientific and technical information related to the Mineral Resource Estimate presented in this news release has been reviewed and approved by César Cerdán, MAIG, who is a Qualified Person ("QP") as defined under NI 43-101.
The Mineral Resource Estimate was prepared using generally accepted mining industry practices, incorporating geological information, QA/QC controls, database validation, sampling, density determinations, geological modeling, and geostatistical methods appropriate for the type of deposit evaluated.
The classification of Mineral Resources reflects the QP's opinion regarding the level of confidence in geological and grade continuity, as well as the quality and quantity of the available information. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. There is no certainty that all or any part of the Inferred Mineral Resources will be converted into higher-confidence categories or ultimately into Mineral Reserves.
Potential Upside: Coarse Gold, Silver Credit, Uncategorized Resource
The current dataset is also subject to certain limitations that support the conservative nature of the estimate. In many areas, the full width of the mineralized structures has not been completely sampled, as historical underground development was largely restricted to linear drifts with limited cross cutting. As a result, portions of the mineralized envelope may remain underrepresented in the current block model.
Furthermore, the resource estimate is based on conventional fire assay methodologies and does not incorporate Metallic Screen Fire Assay analysis unless the results were extraordinarily high. This implies that the potential contribution of coarse gold – that represents a 30% of the recoverable gold based on 2014 metallurgical tests - has not been fully quantified and may represent additional upside.
The Company also notes that silver has not been included in the present resource model, despite its known occurrence within the mineralized system. The incorporation of silver credits in future studies could have a positive impact on the overall project economics.
Finally, several areas of mineralization that demonstrate geological continuity but currently lack sufficient data density have not yet been classified within the resource categories. These zones represent additional exploration targets with potential to expand the resource base.
Strategy Pivot: Transition to Bulk Underground Mining Concept
A previous mineral resource estimation in 2025 was developed on a vein-hosted geological model, applying a base-case cut-off grade of 3.0 g/t Au and focusing solely on narrow, high-grade vein extraction scenarios. The price of gold in early 2025 was
The updated MRE reflects a fundamental shift in approach, with the deposit now modeled as a continuous mineralized body. This revised interpretation supports the strategic pivot to evaluate bulk underground mining methods, driven by improved geological continuity and the current higher gold price environment. This approach allows for the consideration of lower cut-off grades and larger mining volumes, significantly increasing the overall resource base.
Future Plans: Upcoming PFS and Resource Expansion
The Company believes that the current Mineral Resource Estimate represents a conservative baseline for the
Opportunities for resource expansion include the systematic drilling of underexplored areas both laterally and at depth, where geological continuity of mineralization remains open. In addition, several zones within the current model - particularly between sublevels - are considered as inferred resources and could be upgraded to M&I by digitizing the shafts samples from the old stopes.
Using a systematic, data-driven framework for resource expansion across the property, Lode Gold plans to advance these opportunities through targeted drilling, enhanced sampling methodologies, including the application of MSFA — and continued refinement of the geological model as part of its ongoing development strategy.
Near Term Catalyst: Preliminary Feasibility Study
The substantial increase in M&I mineral resource provides a strong basis for advancing the
The Company intends to initiate a Preliminary Feasibility Study (PFS) by Q2 2026, upon receiving the AUP ("Drill Permit") from the
A technical report for the updated mineral resource estimate in accordance with NI 43-101, Standards of Disclosure for Mineral Projects NI 43-101 under the Company's SEDAR+ profile at www.sedarplus.ca will be filed within 45 days of this news release, and on the Company's website at www.lode-gold.com.
About Lode Gold
Lode Gold has key assets in
Dingman Property is an orogenic gold deposit in
Qualified Person Statement
The technical information contained in this press release was reviewed and approved by
César has directed and managed multiple geological modelling projects at Hochschild Mining, Minera Bateas SAC, (a Fortuna Silver Mines company),
César holds a Master's degree in Mining and Mineral Engineering and Diploma in Mineral Economics from the Universidad de
ON BEHALF OF THE COMPANY
CEO & Director
info@lode-gold.com
+1(604) 977-GOLD (4653)
Investor Relations
kevin@lode-gold.com
+1(604) 977-GOLD (4653)
Cautionary Statement Regarding Forward-Looking Information
Neither the
This news release includes "forward-looking statements" and "forward-looking information" within the meaning of Canadian securities legislation. All statements included in this news release, other than statements of historical fact, are forward-looking statements including, without limitation, statements with respect to the use of proceeds, advancement and completion of resource calculation, feasibility studies, and exploration plans and targets. Forward-looking statements include predictions, projections and forecasts and are often, but not always, identified by the use of words such as "anticipate", "believe", "plan", "estimate", "expect", "potential", "target", "budget" and "intend" and statements that an event or result "may", "will", "should", "could" or "might" occur or be achieved and other similar expressions and includes the negatives thereof.
Forward-looking statements are based on a number of assumptions and estimates that, while considered reasonable by management based on the business and markets in which the Company operates, are inherently subject to significant operational, economic, and competitive uncertainties, risks and contingencies. These include assumptions regarding, among other things: the status of community relations and the security situation on site; general business and economic conditions; the availability of additional exploration and mineral project financing; the supply and demand for, inventories of, and the level and volatility of the prices of metals; relationships with strategic partners; the timing and receipt of governmental permits and approvals; the timing and receipt of community and landowner approvals; changes in regulations; political factors; the accuracy of the Company's interpretation of drill results; the geology, grade and continuity of the Company's mineral deposits; the availability of equipment, skilled labour and services needed for the exploration and development of mineral properties; and currency fluctuations.
There can be no assurance that forward-looking statements will prove to be accurate and actual results, and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from the Company's expectations include a deterioration of security on site or actions by the local community that inhibits access and/or the ability to productively work on site, actual exploration results, interpretation of metallurgical characteristics of the mineralization, changes in project parameters as plans continue to be refined, future metal prices, availability of capital and financing on acceptable terms, general economic, market or business conditions, uninsured risks, regulatory changes, delays or inability to receive required approvals, business disruptions, and other exploration or other risks detailed herein and from time to time in the filings made by the Company with securities regulators, including those described under the heading "Risks and Uncertainties" in the Company's most recently filed MD&A. The Company does not undertake to update or revise any forward-looking statements, except in accordance with applicable law.